RIVER COUNTY (G BLOCK)
VGR REAL ESTATE · RAIPUR
Units36
Booked27 of 36As of 2026-09-30
Construction progress82%As of 2026-09-30
Completion2029-04-03Revised · Proposed 2028-12-03
Registered on2023-04-11
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 14 quarters |
| Technical report | |
| Site & area | 4 site details · 36 unit types |
| Construction & progress | 5 progress details · 25 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 95 documents · 7 source links |
Registration
Registration
| Promoter | VGR REAL ESTATE | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | P3CGRERA110423000033 | |
| Registered on | 2023-04-11 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2028-12-03 | |
| Revised completion | 2029-04-03 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Quarterly money flows
| 2023-Q2 | ₹0 |
| 2023-Q3 | ₹0 |
| 2023-Q4 | ₹2,03,000 |
| 2024-Q1 | ₹0 |
| 2024-Q2 | ₹0 |
| 2024-Q3 | ₹0 |
| 2024-Q4 | ₹0 |
| 2025-Q1 | ₹0 |
| 2025-Q2 | ₹5,25,000 |
| 2025-Q3 | ₹0 |
| 2025-Q4 | ₹0 |
| 2026-Q1 | ₹4,90,000 |
| 2026-Q2 | ₹0 |
| 2026-Q3 | ₹10,50,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,319.14 | |
|---|---|---|
| Units | 36 | |
| Booked | 27 | |
| Booked as of | 2026-09-30 |
Unit types
| 3BHK | 146.37 |
| 3BHK | 121.98 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 91.48 |
| 3BHK | 104.55 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 30 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 101.65 |
| 3BHK | 165.32 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 82% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2023-03-20 | |
| Proposed completion | 2028-12-03 | |
| Revised completion | 2029-04-03 |
Quarterly progress
| 2023-Q2 | |
| 2023-Q2 | |
| 2023-Q3 | |
| 2023-Q3 | |
| 2023-Q4 | |
| 2023-Q4 | |
| 2024-Q1 | |
| 2024-Q2 | |
| 2024-Q2 | |
| 2024-Q3 | |
| 2024-Q3 | |
| 2024-Q4 | |
| 2024-Q4 | |
| 2025-Q1 | |
| 2025-Q2 | |
| 2025-Q2 | |
| 2025-Q3 | |
| 2025-Q3 | |
| 2025-Q4 | |
| 2025-Q4 | |
| 2026-Q1 | |
| 2026-Q2 | |
| 2026-Q2 | |
| 2026-Q3 | |
| 2026-Q3 | 82% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | VGR REAL ESTATE | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 20 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/contractor_Reg_Only_View_Application_new.aspx?MyID=Mzc=
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Apartment Details · Sign in to download
- Garage Details · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Stilt Basement Parking · Sign in to download
- Open Parking · Sign in to download
- Common Area Facilities · Sign in to download
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities