Overview
RIVERDALE EXTENTION
Manglam Infra · Sahibzada Ajit Singh Nagar (Mohali)
Units173
Completion2020-06-30Proposed
Valid to2021-12-31
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details · 21 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 15 documents · 29 source links |
Registration
Registration
| Promoter | Manglam Infra | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS79-PR0462 | |
| Valid to | 2021-12-31 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | Completion Certificate | |
| Proposed completion | 2020-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| CLU Certificate | ||
| License as Promoter from competent Authority | 2017-02-14 | |
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | Permissions (Received) | 2019-03-02 |
| Consent details of actual owner of Land | ||
| Consent details of actual owner of Land |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹25,03,69,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 27,114.63 | |
|---|---|---|
| Units | 173 |
Unit types
| Type | Carpet (m²) | Units | Tower |
|---|---|---|---|
| Plotted Development | 95.427 | 152 | RIVERDALE EXTENTION |
| Commercial Plots | 30 | 21 | COMMERCIAL PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-02-22 | |
|---|---|---|
| Proposed completion | 2020-06-30 |
Quarterly progress
| 2019-Q2 | 2021-03-05 |
| 2019-Q3 | 2021-03-05 |
| 2019-Q4 | 2021-03-05 |
| 2020-Q1 | 2021-03-05 |
| 2020-Q2 | 2021-03-05 |
| 2020-Q3 | 2021-03-05 |
| 2020-Q4 | 2021-03-05 |
| 2021-Q1 | 2021-04-16 |
| 2021-Q2 | 2022-05-31 |
| 2021-Q3 | 2022-05-31 |
| 2021-Q4 | 2022-05-31 |
| 2022-Q1 | 2022-05-31 |
| 2022-Q2 | 2022-09-26 |
| 2022-Q3 | 2022-10-10 |
| 2022-Q4 | 2023-01-11 |
| 2023-Q1 | 2023-05-29 |
| 2023-Q2 | 2023-08-19 |
| 2023-Q3 | 2023-12-11 |
| 2023-Q4 | 2024-01-25 |
| 2024-Q1 | 2024-04-13 |
| 2024-Q2 | 2024-07-08 |
Extensions
| Valid to |
|---|
| 2021-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Manglam Infra | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Bank of India | |
| Other projects in this city pack | 5 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=10800&inPromoter_ID=1664&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- License as Promoter from competent Authority · 2017-02-14
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-03-02
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- CLU Certificate
- License as Promoter from competent Authority · 2017-02-14
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2019-03-02
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- 2019-Q2 · 2021-03-05
- 2019-Q3 · 2021-03-05
- 2019-Q4 · 2021-03-05
- 2020-Q1 · 2021-03-05
- 2020-Q2 · 2021-03-05
- 2020-Q3 · 2021-03-05
- 2020-Q4 · 2021-03-05
- 2021-Q1 · 2021-04-16
- 2021-Q2 · 2022-05-31
- 2021-Q3 · 2022-05-31
- 2021-Q4 · 2022-05-31
- 2022-Q1 · 2022-05-31
- 2022-Q2 · 2022-09-26
- 2022-Q3 · 2022-10-10
- 2022-Q4 · 2023-01-11
- 2023-Q1 · 2023-05-29
- 2023-Q2 · 2023-08-19
- 2023-Q3 · 2023-12-11
- 2023-Q4 · 2024-01-25
- 2024-Q1 · 2024-04-13
- 2024-Q2 · 2024-07-08