DOSLJaipur, Rajasthan Workspace

Overview

RIYASAT GOVINDAM BLOCK-A

RIYASAT INFRATECH DEVELOPERS LLP · Jaipur
Units117
Booked66 of 117As of 2023-09-30
Completion2024-12-31Revised · Proposed 2023-02-14
Registered on2023-02-19
Valid to2024-12-31

Sections

Property title & search report
Contract & costs3 cost heads · 1 quarter
Technical report
Site & area6 site details · 45 unit types
Construction & progress3 progress details · 1 quarter
Developer & finance
Developer4 developer details
The evidence
Sources64 documents · 6 source links

Registration

Registration

PromoterRIYASAT INFRATECH DEVELOPERS LLP
DistrictJaipur
RegulatorRajasthan RERA
Registration numberRAJ/P/2023/2388
Registered on2023-02-19
Valid to2024-12-31
Project typePlotted
Status (as filed)COMPLETED
Proposed completion2023-02-14
Revised completion2024-12-31