Overview
RK TECH MAYOORAM
RK TECH DEVELOPERS · Visakhapatnam
Units10
Completion2029-03-24Proposed
Registered on2026-04-26
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 10 unit types |
| Construction & progress | 2 progress details · 2 quarters |
| Developer & finance | |
| Developer | 2 developer details · 1 professional firm |
| The evidence | |
| Sources | 24 documents · 9 source links |
Registration
Registration
| Promoter | RK TECH DEVELOPERS | |
|---|---|---|
| District | Visakhapatnam | |
| Regulator | AP RERA | |
| Registration number | P03240106578 | |
| Registered on | 2026-04-26 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-03-24 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1086/1096/B/Z8/CDA/2025 | 2026-03-24 | Director,Town and Country Planning |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹92,00,000 | |
|---|---|---|
| Construction | ₹2,06,10,000 | |
| Total | ₹2,98,10,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 250.58 | |
|---|---|---|
| Built-up (m²) | 1,084.86 | |
| Towers | 1 | |
| Units | 10 |
Unit types
| 3BHK | 70.3 | 1 | RK TECH PARADISE | FIRST |
| 2BHK | 58.57 | 1 | RK TECH PARADISE | FIRST |
| 3BHK | 70.3 | 1 | RK TECH PARADISE | FOURTH |
| 2BHK | 58.57 | 1 | RK TECH PARADISE | FOURTH |
| 3BHK | 70.3 | 1 | RK TECH PARADISE | GROUND |
| 2BHK | 58.57 | 1 | RK TECH PARADISE | GROUND |
| 3BHK | 70.3 | 1 | RK TECH PARADISE | SECOND |
| 2BHK | 58.57 | 1 | RK TECH PARADISE | SECOND |
| 3BHK | 70.3 | 1 | RK TECH PARADISE | THIRD |
| 2BHK | 58.57 | 1 | RK TECH PARADISE | THIRD |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2026-03-24 | |
|---|---|---|
| Proposed completion | 2029-03-24 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2026-Q2 | 2026-07-14 |
| 2026-Q3 | 2026-10-10 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RK TECH DEVELOPERS | |
|---|---|---|
| Other projects in this city pack | 2 |
Professional firms
| Role | Firm |
|---|---|
| CA | THEEGELA ASSOCIATES |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFT6gPp1F3TRqELpdAsWSNzG0mtE+YsNAVj6yWWbl21KDk9oMRbKdoVKJrF/UkC9gNWpTEuvcONrd8sHRj7rJNA2CNF2YaUpMO8p4QCufgUYQ
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE