Overview
ROHTAK GREEN
BESTPLUS DEVELOPERS PRIVATE LIMITED · Rohtak
Units162
Completion2019-12-13Proposed
Registered on2017-09-20
Valid to2021-06-30
Approvals4
Cases4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 4 cases · 2 registration details |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 19 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 5 documents · 3 source links |
Registration
Registration
| Promoter | BESTPLUS DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| District | Rohtak | |
| Regulator | HRERA Panchkula | |
| Registration number | 238 OF 2017 DATED 20.09.2017 | |
| Registered on | 2017-09-20 | |
| Valid to | 2021-06-30 | |
| Status (as filed) | Lapsed Project | |
| Proposed completion | 2019-12-13 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | LICENSE NO. 62 OF 2017 DATED 28.07.2017. | Town & Country Planning Department | |
| Layout Plan | 2017-07-28 | ||
| Building Plan | |||
| I. LICNESE NO. 62 OF 2017 | 2017-07-28 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA-PKL-3182-2022 | HRERA Panchkula | Pending |
| RERA-PKL-2149-2019 | HRERA Panchkula | |
| RERA-PKL-1077-2020 | HRERA Panchkula | Disposed |
| RERA-PKL-1859-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 4 |
|---|
Registration status
| Status | Lapsed Project | |
|---|---|---|
| Valid to | 2021-06-30 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,94,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹19,21,50,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 200 | |
|---|---|---|
| Units | 162 |
Unit types
| Plot | 1 | |
| Plot | 27 | |
| Plot | 33 | |
| Plot | 1 | |
| Plot | 6 | |
| Plot | 1 | |
| Plot | 8 | |
| Plot | 7 | |
| Plot | 1 | |
| Plot | 2 | |
| Plot | 10 | |
| Plot | 1 | |
| Plot | 7 | |
| Plot | 12 | |
| Plot | 22 | |
| Plot | 9 | |
| Plot | 1 | |
| Plot | 13 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-07-28 | |
|---|---|---|
| Proposed completion | 2019-12-13 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BESTPLUS DEVELOPERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | YES BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/MjM4IG9mIDIwMTcgZGF0ZWQgMjAuMDkuMjAxNw==
- https://haryanarera.gov.in/view_project/project_preview_open/2184
- Registration Certificate · 2017-09-20
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2022-11-03 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2022-11-03
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2022-11-03
- Extension of Registration of project · 2021-03-17 · Sign in to download