Overview
RPS09/2025
YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY · SECTOR-18,YEIDA
Units274
Completion2030-06-30Proposed
Registered on2025-04-11
Valid to2030-06-30
Approvals1
Complaints0As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 0 project complaints · 339 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 2 progress details · 2 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 15 documents · 10 source links |
Registration
Registration
| Promoter | YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY | |
|---|---|---|
| District | Gautam Buddha Nagar | |
| Locality | SECTOR-18,YEIDA | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ103634/04/2025 | |
| Registered on | 2025-04-11 | |
| Valid to | 2030-06-30 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2030-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | DS-01PLNG/N-225 TO 227 | 2024-10-28 | 2029-10-27 | Yamuna Expressway Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 339 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,45,14,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,05,870 | |
|---|---|---|
| Units | 274 |
Unit types
| Type | Units |
|---|---|
| 150 to 200 sqm | 274 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-07-01 | |
|---|---|---|
| Proposed completion | 2030-06-30 |
Quarterly progress
| Quarter | Progress |
|---|---|
| 2025-Q3 | 0% |
| 2026-Q3 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | YAMUNA EXPRESSWAY INDUSTRIAL DEVLOPMENT AUTHORITY | |
|---|---|---|
| Type | Other | |
| Other projects in this city pack | 15 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=uDsn9ZxPbAI=&hfFlag=9emr4VdBw22M7BGjKtJWMPDI4s5cHQZP&NPJ6RAme=RDBoHScE7ddPpxmcTplbfA==&PaURJEMAN4=ZL9MNERkNdbchzOmwk2jLk6vbv9eC7zM&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/WebService1.asmx/loadPlot_new
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=GAUTAM%20BUDDHA%20NAGAR
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=uDsn9ZxPbAI=
- Commencement Certificate · 2025-02-28
- Other Plan(If Any) · 2025-02-06
- Waste Disposal Plan · 2025-02-06
- Water Supply Plan · 2025-02-06
- Electricity Supply Plan · 2025-02-28
- CA CERTIFICATE · 2025-03-20 · Sign in to download
- ARCHITECT CERTIFICATE · 2025-02-28 · Sign in to download
- ENGINEERS CERTIFICATE · 2025-03-07 · Sign in to download
- Other · 2025-04-05 · Sign in to download
- 2025-Q3 CA certificate
- 2025-Q3 Architect certificate
- 2025-Q3 Engineer certificate
- 2026-Q3 CA certificate
- 2026-Q3 Architect certificate
- 2026-Q3 Engineer certificate
- 2025-Q3
- 2026-Q3