Overview
RUKMANI VIHAR
RUKMANI INFRASTRUCTURE PVT. LTD. · RAIGARH
Units13
Booked11 of 13As of 2026-06-30
Construction progress100%As of 2026-06-30
Completion2025-07-07Revised · Proposed 2018-12-31
Registered on2018-07-10
Cases4
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 4 cases |
| Contract & costs | 2 cost heads · 31 quarters |
| Technical report | |
| Site & area | 3 site details · 13 unit types |
| Construction & progress | 4 progress details · 31 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 134 documents · 10 source links |
Registration
Registration
| Promoter | RUKMANI INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| District | RAIGARH | |
| Regulator | CG RERA | |
| Registration number | PCGRERA100718000515 | |
| Registered on | 2018-07-10 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2018-12-31 | |
| Revised completion | 2025-07-07 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| M-COM-2025-02721 | CG RERA | Complaint | Disposed | 2025-08-13 |
| SM-EXP-2024-02238 | CG RERA | Complaint | Disposed | 2024-07-05 |
| M-PRO-2023-01951 | CG RERA | Complaint | Disposed | 2023-10-25 |
| M-COM-2019-00485 | CG RERA | Complaint | Disposed | 2019-06-13 |
Complaints & cases
| Cases | 4 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹7,68,000 | |
|---|---|---|
| Construction | ₹84,94,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹13,664 |
| 2020-Q1 | ₹12,590.4 |
| 2020-Q2 | ₹12,590.4 |
| 2020-Q3 | ₹12,590.4 |
| 2020-Q4 | ₹9,01,705.4 |
| 2021-Q1 | ₹87,76,687.7 |
| 2021-Q2 | ₹9,01,611 |
| 2021-Q3 | ₹9,01,593.3 |
| 2021-Q4 | ₹9,01,575.6 |
| 2022-Q1 | ₹3,01,137.6 |
| 2022-Q2 | ₹2,87,479.49 |
| 2022-Q3 | ₹37,462.01 |
| 2022-Q4 | ₹37,444.31 |
| 2023-Q1 | ₹37,444.31 |
| 2023-Q2 | ₹0 |
| 2023-Q3 | ₹6,13,998.4 |
| 2023-Q4 | ₹6,13,998.4 |
| 2024-Q1 | ₹14,069 |
| 2024-Q2 | ₹3,15,319 |
| 2024-Q4 | ₹0 |
| 2025-Q1 | ₹0 |
| 2025-Q2 | ₹0 |
| 2025-Q3 | ₹0 |
| 2025-Q4 | ₹0 |
| 2026-Q1 | ₹0 |
| 2026-Q2 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 13 | |
|---|---|---|
| Booked | 11 | |
| Booked as of | 2026-06-30 |
Unit types
| Plot-1 | 1 | 1 |
| Plot-2 | 1 | 1 |
| Plot-3 | 1 | 1 |
| Plot-4 | 1 | 1 |
| Plot-5 | 1 | 1 |
| Plot-6 | 1 | 1 |
| Plot-7 | 1 | 1 |
| Plot-8 | 1 | 1 |
| Plot-9 | 1 | 0 |
| Plot-10 | 1 | 1 |
| Plot-11 | 1 | 1 |
| Plot-12 | 1 | 1 |
| Plot-13 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2018-12-31 | |
| Revised completion | 2025-07-07 |
Quarterly progress
| 2018-Q3 | 90% |
| 2018-Q4 | 95% |
| 2019-Q1 | 100% |
| 2019-Q2 | 100% |
| 2019-Q3 | 100% |
| 2019-Q4 | 100% |
| 2020-Q1 | 100% |
| 2020-Q2 | 100% |
| 2020-Q3 | 100% |
| 2020-Q4 | 100% |
| 2021-Q1 | 100% |
| 2021-Q2 | 100% |
| 2021-Q3 | 100% |
| 2021-Q4 | 100% |
| 2022-Q1 | 100% |
| 2022-Q2 | 100% |
| 2022-Q3 | 100% |
| 2022-Q4 | 100% |
| 2023-Q1 | 100% |
| 2023-Q2 | 100% |
| 2023-Q3 | 100% |
| 2023-Q4 | 100% |
| 2024-Q1 | 100% |
| 2024-Q2 | 100% |
| 2024-Q4 | 100% |
| 2025-Q1 | 100% |
| 2025-Q2 | 100% |
| 2025-Q3 | 100% |
| 2025-Q4 | 100% |
| 2026-Q1 | 100% |
| 2026-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | RUKMANI INFRASTRUCTURE PVT. LTD. | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NTk5
- https://rera.cgstate.gov.in/cause_list.aspx
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2025-08-13 · Sign in to download
- Final order · 2024-07-05 · Sign in to download
- Final order · 2023-10-25 · Sign in to download
- Final order · 2019-06-13 · Sign in to download
- Interim order · 2025-05-30 · Sign in to download
- Interim order · 2024-05-08 · Sign in to download
- M-COM-2025-02721 · Sign in to download
- SM-EXP-2024-02238 · Sign in to download
- M-PRO-2023-01951 · Sign in to download
- M-COM-2019-00485 · Sign in to download