Runwal Gardens Phase 4 Bldg No. 37
Overview
Runwal Gardens Phase 4 Bldg No. 37
Overview
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Not verified |
| Approvals | – | – | – | – |
| Disputes & cases | – | – | – | – |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
Title & ownership
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Developer's project loan | ₹8.29 Cr secured |
|---|
Approvals
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 30 Jun 2027 |
| Registration number | P51700033206 | |
|---|---|---|
| Registered | 9 Feb 2022 |
Disputes & cases
Builder: Runwal Residency Private Limited
The filing names no land owners, so there is no name to search.
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| None listed. | |||||||
| Filed on | Case no. | Filed at | Location | Filed by | Against | What it's about | Status |
|---|---|---|---|---|---|---|---|
| Search pending. | |||||||
MahaRERA lists complaints by case number. A complaint that names this registration is listed here.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
17 other registrations under this promoter's exact name in Maharashtra; a complaint on one is listed when MahaRERA lists it.
| Filed on | Case no. | Filed at | Location | Filed by | What it's about | Status |
|---|---|---|---|---|---|---|
| None listed. | ||||||
Contract & costs
We haven't verified this for this project yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
| Carpet area | Units filed | Sold | Unsold | Median ₹/sq ft carpet |
|---|---|---|---|---|
| 358 sq ft · 33.23 sq m | 2 | 2 | 0 | – |
| 489–496 sq ft · 45.4–46.1 sq m | 106 | 90 | 16 | ₹11,485 |
| 562–564 sq ft · 52.2–52.4 sq m | 34 | 28 |
Location & risks
Construction & progress
Developer
Loan & collateral
| Developer's project loan | ₹8.29 Cr secured |
|---|
Data room
Source: MahaRERA project page and the documents filed there, as read by us. 130 documents filed with MahaRERA, identity papers and photographs, are left out of this list.
| Construction & progress | – | – | – | – |
|---|
| Developer & finance |
|---|
| Developer | – | – | – | – |
|---|
| Loan & collateral | – | – | – | – |
|---|
All projects in Thane → · All projects in Mumbai → (12 of 3,098 shown here)
Everything here is as filed by the promoter with MahaRERA, and can be stale or wrong at source. Verify against certified records before you transact.
| ₹11,338 |
| 636–669 sq ft · 59.1–62.1 sq m | 111 | 97 | 14 | ₹10,082 |
| 753–760 sq ft · 70.0–70.6 sq m | 29 | 23 | 6 | ₹8,017 |
| Carpet area | Unsold units | Carpet area, total |
|---|---|---|
| 489–496 sq ft · 45.4–46.1 sq m | 16 | 7,887 sq ft |
| 562–564 sq ft · 52.2–52.4 sq m | 6 | 3,375 sq ft |
| 636–669 sq ft · 59.1–62.1 sq m | 14 | 9,139 sq ft |
| 753–760 sq ft · 70.0–70.6 sq m | 6 | 4,525 sq ft |
| All unsold | 42 | 24,926 sq ft |
| RERA completion date | 30 Jun 2027 | |
|---|---|---|
| Registered | 9 Feb 2022 | |
| Completion date first filed | 31 Mar 2026 |
| Architect's certificate, Form 1 | 5 filed · latest filed 19 Oct 2026 | |
|---|---|---|
| Engineer's certificate, Form 2 | 4 filed · latest filed 16 Oct 2026 |
Land · ₹15.45 Cr 12.4%Development · ₹108.63 Cr 87.6%
| Estimated cost, at registration | ₹124.08 Cr |
|---|
Sold 85%Unsold 15%
| Units filed | 282 | |
|---|---|---|
| Sold | 238 · 84% | |
| Unsold | 42 |
| Escrow balance | ₹5,80,293.7 (INR) | |
|---|---|---|
| Filed withdrawal amount | ₹90,58,67,096.2 (INR) |
| MahaRERA registrations under this promoter | 18 | |
|---|---|---|
| Marked completed | 0 | |
| Past promised date, not completed | 8 | |
| Other phases under this promoter name | 17 | |
| With a filed extension or completion | 12 (0 completed, 12 extended) | |
| Average schedule slip | 17 months |