Overview
RUPA TOWER
GANPATI RESIDENCY PRIVATE LIMITED · Patna
Units0
Completion2021-07-20Proposed
Registered on2019-01-17
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 22 documents · 15 source links |
Registration
Registration
| Promoter | GANPATI RESIDENCY PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00385-2/531/R-340/2019 | |
| Registered on | 2019-01-17 | |
| Project type | Commercial | |
| Status (as filed) | Completed | |
| Proposed completion | 2021-07-20 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,004.37 | |
|---|---|---|
| Built-up (m²) | 2,328.36 | |
| FAR | 2.31 | |
| Towers | 0 | |
| Units | 0 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Shop | 0 | RUPA TOWER |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-08-20 | |
|---|---|---|
| Proposed completion | 2021-07-20 |
Quarterly progress
| 2022-Q1 | 2022-10-26 |
| 2021-Q4 | 2022-01-24 |
| 2021-Q3 | 2021-10-23 |
| 2021-Q2 | 2021-07-12 |
| 2021-Q1 | 2022-01-25 |
| 2020-Q4 | 2021-01-21 |
| 2020-Q3 | 2022-03-30 |
| 2019-Q4 | 2020-02-25 |
| 2019-Q3 | 2020-02-25 |
| 2019-Q2 | 2020-02-25 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | GANPATI RESIDENCY PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Indusind Bank | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP105201800385-2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP105201800385-2
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Q4-Jan to Mar / 2021-2022 · 2022-10-26
- Q3-Oct to Dec / 2021-2022 · 2022-01-24
- Q2-Jul to Sep / 2021-2022 · 2021-10-23
- Q1-Apr to Jun / 2021-2022 · 2021-07-12
- Q4-Jan to Mar / 2020-2021 · 2022-01-25
- Q3-Oct to Dec / 2020-2021 · 2021-01-21
- Q2-Jul to Sep / 2020-2021 · 2022-03-30
- Q3-Oct to Dec / 2019-2020 · 2020-02-25
- Q2-Jul to Sep / 2019-2020 · 2020-02-25
- Q1-Apr to Jun / 2019-2020 · 2020-02-25
- Notice of Commencement
- 2022-Q1 · 2022-10-26
- 2021-Q4 · 2022-01-24
- 2021-Q3 · 2021-10-23
- 2021-Q2 · 2021-07-12
- 2021-Q1 · 2022-01-25
- 2020-Q4 · 2021-01-21
- 2020-Q3 · 2022-03-30
- 2019-Q4 · 2020-02-25
- 2019-Q3 · 2020-02-25