DOSLChhattisgarh Workspace

Overview

S B GOLF LINKS

BAFNA EARTH MOVERS LIMITED · DURG
Units204
Booked31 of 204As of 2024-03-31
Construction progress89%As of 2024-03-31
Completion2026-10-06Revised · Proposed 2021-06-30
Registered on2019-02-06
Approvals1
Cases1

Sections

Property title & search report
Approvals1 approval
Disputes & cases1 case
Contract & costs2 cost heads · 21 quarters
Technical report
Site & area3 site details · 204 unit types
Construction & progress4 progress details · 21 quarters
Developer & finance
Developer3 developer details
The evidence
Sources111 documents · 8 source links

Registration

Registration

PromoterBAFNA EARTH MOVERS LIMITED
DistrictDURG
RegulatorCG RERA
Registration numberPCGRERA060219000907
Registered on2019-02-06
Project typePlotted Development
Status (as filed)Ongoing
Proposed completion2021-06-30
Revised completion2026-10-06