Overview
S.R. MALL
SHREE RAVI HOMES PRIVATE LIMITED · Patna
Units107
Booked0 of 107As of 2026-06-30
Construction progress44%As of 2026-06-30
Completion2027-04-27Proposed
Registered on2022-03-30
Valid to2027-04-27
Approvals5
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 5 unit types |
| Construction & progress | 4 progress details · 17 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 29 documents · 23 source links |
Registration
Registration
| Promoter | SHREE RAVI HOMES PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00547-3/32/R-1313/2022 | |
| Registered on | 2022-03-30 | |
| Valid to | 2027-04-27 | |
| Project type | Commercial | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2027-04-27 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2022-03-02 | PATNA MUNICIPAL CORPORATION | |
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc. | |||
| Notice of Commencement | |||
| Environment Clearance | 0 | ||
| Fire NOC | 2027-04-27 | YES |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹15,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,886.39 | |
|---|---|---|
| Built-up (m²) | 12,767.16 | |
| FAR | 3.34 | |
| Towers | 1 | |
| Units | 107 | |
| Booked | 0 | |
| Booked as of | 2026-06-30 |
Unit types
| Convenience Store | 10 | S.R. Mall |
| Food Court | 20 | S.R. Mall |
| Shop | 70 | S.R. Mall |
| Restaurant | 3 | S.R. Mall |
| AUDI | 4 | S.R. Mall |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 44% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2022-04-28 | |
| Proposed completion | 2027-04-27 |
Quarterly progress
| 2026-Q2 | 2026-07-31 | 44% | 0 |
| 2026-Q1 | 2026-04-30 | ||
| 2025-Q4 | 2026-01-31 | ||
| 2025-Q3 | 2025-10-29 | ||
| 2025-Q2 | 2025-08-31 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-15 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-07-15 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-15 | ||
| 2022-Q4 | 2023-01-16 | ||
| 2022-Q3 | 2022-10-17 | ||
| 2022-Q2 | 2022-07-11 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHREE RAVI HOMES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | Union Bank of India | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP276201800547-3
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP276201800547&ld=pan&pj=RERAP276201800547-3&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP276201800547-3
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-31
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-30
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-31
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-29
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-31
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-15
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-15
- Q3-Oct to Dec / 2022-2023 · 2023-01-16
- Q2-Jul to Sep / 2022-2023 · 2022-10-17
- Q1-Apr to Jun / 2022-2023 · 2022-07-11
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Notice of Commencement
- 2026-Q1 · 2026-04-30
- 2025-Q4 · 2026-01-31
- 2025-Q3 · 2025-10-29
- 2025-Q2 · 2025-08-31
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-15
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-15
- 2022-Q4 · 2023-01-16
- 2022-Q3 · 2022-10-17
- 2022-Q2 · 2022-07-11