Overview
SAFFRON ESTATE
SAMYAK PROPERTIES AND INFRASTRUCTURE PRIVATE LIMITED · Sonipat
Units102
Completion2023-08-30Proposed
Valid to2023-08-31
Approvals5
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 5 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 13 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 12 documents · 3 source links |
Registration
Registration
| Promoter | SAMYAK PROPERTIES AND INFRASTRUCTURE PRIVATE LIMITED | |
|---|---|---|
| District | Sonipat | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-SNP-156-2019 | |
| Valid to | 2023-08-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2023-08-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 90 OF 2019 | Town & Country Planning Department | |
| Layout Plan | 2019-08-01 | ||
| Building Plan | |||
| I. LICENSE | 2019-08-07 | ||
| II. LAYOUT PLAN | 2019-08-01 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Status |
|---|---|---|
| RERA-PKL-1986-2022 | HRERA Panchkula | Disposed |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,43,17,999.99999999 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹20,14,24,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 0 | |
|---|---|---|
| Units | 102 |
Unit types
| Plot | 36 | |
| Plot | 14 | |
| Plot | 3 | |
| Plot | 33 | |
| Plot | 6 | |
| Plot | 4 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2019-10-01 | |
|---|---|---|
| Proposed completion | 2023-08-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAMYAK PROPERTIES AND INFRASTRUCTURE PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/SFJFUkEtUEtMLVNOUC0xNTYtMjAxOQ==
- https://haryanarera.gov.in/view_project/project_preview_open/810
- Registration Certificate
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2019-08-13
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2019-08-26 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2019-08-20
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2019-08-20
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2019-08-27 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2019-08-27 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2019-08-20
- ZONING PLAN · 2019-08-20
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2019-08-13
- DEMARCATION PLAN · 2019-08-20
- completion certificate uploaded. · 2024-09-10 · Sign in to download