Overview
SAHEB SOCIETY
SAHEB GRIH NIRMAN SAHKARI SAMITI · RAIPUR
Units59
Booked38 of 59As of 2024-03-31
Construction progress100%As of 2024-03-31
Completion2019-03-31Proposed
Registered on2018-08-21
Approvals3
Cases2
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 2 cases |
| Contract & costs | 2 cost heads · 23 quarters |
| Technical report | |
| Site & area | 3 site details · 59 unit types |
| Construction & progress | 3 progress details · 23 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 98 documents · 11 source links |
Registration
Registration
| Promoter | SAHEB GRIH NIRMAN SAHKARI SAMITI | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA210818000712 | |
| Registered on | 2018-08-21 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2019-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| SM-EXP-2026-03692 | CG RERA | Complaint | Disposed | 2026-08-31 |
| SM-EXP-2024-02283 | CG RERA | Complaint | Disposed | 2024-09-23 |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,59,40,000 | |
|---|---|---|
| Construction | ₹1,67,43,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹0 |
| 2019-Q2 | ₹0 |
| 2019-Q3 | ₹0 |
| 2019-Q4 | ₹7,66,570 |
| 2020-Q1 | ₹1,44,190 |
| 2020-Q2 | ₹3,78,671.8 |
| 2020-Q3 | ₹0.8 |
| 2020-Q4 | ₹0.8 |
| 2021-Q1 | ₹0.8 |
| 2021-Q2 | ₹0.8 |
| 2021-Q3 | ₹0.8 |
| 2021-Q4 | ₹0.8 |
| 2022-Q1 | ₹0.8 |
| 2022-Q2 | ₹0.8 |
| 2022-Q3 | ₹0.8 |
| 2022-Q4 | ₹0.8 |
| 2023-Q1 | ₹0.8 |
| 2023-Q2 | ₹0.8 |
| 2023-Q3 | ₹0.8 |
| 2023-Q4 | ₹0.8 |
| 2024-Q1 | ₹0.8 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 59 | |
|---|---|---|
| Booked | 38 | |
| Booked as of | 2024-03-31 |
Unit types
| B-01-1 | 1 | 1 |
| B-02-2 | 1 | 1 |
| B-03-3 | 1 | 1 |
| B-04-4 | 1 | 1 |
| B-05-5 | 1 | 1 |
| B-06-6 | 1 | 1 |
| B-07-7 | 1 | 1 |
| B-08-8 | 1 | 1 |
| B-09-9 | 1 | 1 |
| B-10-10 | 1 | 1 |
| B-11-11 | 1 | 1 |
| B-12-12 | 1 | 1 |
| B-13-13 | 1 | 1 |
| B-14-14 | 1 | 0 |
| B-15-15 | 1 | 1 |
| B-16-16 | 1 | 1 |
| B-17-17 | 1 | 1 |
| B-18-18 | 1 | 1 |
| B-19-19 | 1 | 1 |
| B-20-20 | 1 | 0 |
| B-21-21 | 1 | 1 |
| B-22-22 | 1 | 1 |
| LIG-01-23 | 1 | 1 |
| LIG-02-24 | 1 | 1 |
| LIG-03-25 | 1 | 1 |
| LIG-04-26 | 1 | 1 |
| LIG-05-27 | 1 | 1 |
| LIG-06-28 | 1 | 1 |
| LIG-07-29 | 1 | 1 |
| LIG-08-30 | 1 | 0 |
| LIG-09-31 | 1 | 0 |
| C-01-32 | 1 | 1 |
| C-02-33 | 1 | 0 |
| C-03-34 | 1 | 1 |
| C-04-35 | 1 | 1 |
| C-05-36 | 1 | 1 |
| C-06-37 | 1 | 1 |
| C-07-38 | 1 | 1 |
| C-08-39 | 1 | 1 |
| C-09-40 | 1 | 1 |
| C-10-41 | 1 | 0 |
| C-11-42 | 1 | 0 |
| C-12-43 | 1 | 0 |
| C-13-44 | 1 | 0 |
| C-14-45 | 1 | 0 |
| C-15-46 | 1 | 1 |
| C-16-47 | 1 | 1 |
| C-17-48 | 1 | 1 |
| C-18-49 | 1 | 0 |
| C-19-50 | 1 | 0 |
| C-20-51 | 1 | 0 |
| A-1-52 | 1 | 0 |
| A-2-53 | 1 | 0 |
| A-3-54 | 1 | 0 |
| A-4-55 | 1 | 0 |
| A-5-56 | 1 | 0 |
| A-6-57 | 1 | 0 |
| A-7-58 | 1 | 0 |
| A-8-59 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2024-03-31 | |
| Proposed completion | 2019-03-31 |
Quarterly progress
| 2018-Q3 | 51% |
| 2018-Q4 | 51% |
| 2019-Q1 | 51% |
| 2019-Q2 | 54% |
| 2019-Q3 | 58% |
| 2019-Q4 | 65% |
| 2020-Q1 | 68% |
| 2020-Q2 | 71% |
| 2020-Q3 | 73% |
| 2020-Q4 | 85% |
| 2021-Q1 | 90% |
| 2021-Q2 | 90% |
| 2021-Q3 | 92% |
| 2021-Q4 | 95% |
| 2022-Q1 | 99% |
| 2022-Q2 | 99% |
| 2022-Q3 | 99% |
| 2022-Q4 | 99% |
| 2023-Q1 | 99% |
| 2023-Q2 | 99% |
| 2023-Q3 | 100% |
| 2023-Q4 | 100% |
| 2024-Q1 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAHEB GRIH NIRMAN SAHKARI SAMITI | |
|---|---|---|
| Type | Authority | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_interim_order.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=Nzk5
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2026-08-31 · Sign in to download
- Final order · 2024-09-23 · Sign in to download
- Interim order · 2024-05-31 · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities
- SM-EXP-2026-03692 · Sign in to download
- SM-EXP-2024-02283 · Sign in to download