Title & ownership
Approvals
| Power NOC | Filed with the registration | |
|---|---|---|
| Fire NOC | Filed with the registration | |
| Environmental clearance | Filed with the registration | |
| Airport height NOC | permissible top elevation 1049.05 m above mean sea level | |
| KSPCB | Filed with the registration | |
| Water supply NOC | Filed with the registration |
Disputes & cases
Contract & costs
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Valuation
We haven't verified the rest of this yet.
Sign in first, then it is one click.
Location & risks
Construction & progress
Developer
| Estimated cost, at registration | ₹141.50 Cr |
|---|
Loan & collateral
| Escrow bank | Union Bank of India · Ghandhi Nagar |
|---|
Data room
77 documents filed with K-RERA for this project
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
Survey plots around an approximate filed pin, with its uncertainty ring, on satellite imagery. The outlines are the land of each survey number, not buildings. Survey plots around an approximate filed pin. The dashed ring is 1 km: nine in ten approximate pins checked against surveyed land sat within it, so the site is most likely somewhere inside it, not at its centre. This project's survey numbers are not matched to the plots yet, so none is marked as its land.
| Property title & search report | ||||
|---|---|---|---|---|
| Title & ownership | – | – | – | Locked |
| Approvals | 1 | – | – | Red flag |
| Disputes & cases | – | – | – | Locked |
| Contract & costs | – | – | – | Not verified |
| Technical report | ||||
| Valuation | – | – | – | Not verified |
| Location & risks | – | – | – | – |
| Construction & progress | – | – | – | – |
| Developer & finance | ||||
| Developer | – | – | – | – |
| Loan & collateral | – | – | – | – |
| Adarsh Greens Phase 1Extended to 31-10-2026 | ADARSH HAVEN PRIVATE LIMITED | Apartment | 366–635 sqft carpet (as filed) | Oct 2025 |
| Adarsh Greens Phase 2Extended to 31-05-2027 | ADARSH HAVEN PRIVATE LIMITED | Apartment | 635 sqft carpet (as filed) | May 2026 |
| Adhishree SunshineWithdrawn | ADHISHREE VENTURES INDIA PVT LTD | Apartment | – | Sep 2021 |
| Adi's North LakeCompleted (regulator flag) | ADI DEVELOPERS | Apartment | 1,435 sqft carpet (as filed) | Completed |
| Affinity SowparnikaCompleted · OC 29-04-2019 | Affinity Projects | Apartment | – | Completed |
| Anugrha ApartmentLapsed · completion date passed | Gayathri Krishna Infrastructure Prospects Private limited | Apartment | – | Apr 2018 |
| Arun Auroville Phase ILapsed · completion date passed | Arun Shelters Pvt Ltd | Apartment | 2,716 sqft carpet (as filed) | May 2021 |
| Arvind SkylandsCompleted · OC 03-02-2020 | Arvind SmartSpaces Limited | Apartment | 1,063 sqft carpet (as filed) | Completed |
8 of 44 other projects in Jakkur, A to Z. Status is taken from each project's own filing.
All 46 projects in Jakkur → · sai kalyan builders and developers private limited's track record →
Everything here is as filed by the promoter with Karnataka RERA or as recorded in Bhoomi land records, and can be stale or wrong at source. Verify against certified records before you transact. Open Sai Kalyan Water Edge in the interactive atlas
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| RERA extensions | None on the filing | |
|---|---|---|
| RERA completion date | 31 Dec 2027 | |
| Registration status | Withdrawn | Red flag |
₹99 for this report opens Title & ownership, Disputes & cases and Documents for this project, yours to read for good.
| Forfeiture, agreement | 20% of the sale consideration |
|---|
| 4square Park Sierra | about 1 km | Locked |
|---|
| Legacy Salvador | about 1.5 km | Locked |
|---|
| Cumins Sanctum | about 2 km | Locked |
|---|
| Assetz Soho & Sky Phase 1b | about 2 km | Locked |
|---|
| Assetz Soho & Sky | about 2.5 km | Locked |
|---|
| Godrej Aveline | about 3 km | Locked |
|---|
| Sumadhura Epitome | about 3.5 km | Locked |
|---|
| Sobha City Athena | about 3.5 km | Locked |
|---|
| Sumadhura Solea | about 3.5 km | Locked |
|---|
| Sobha Dream Gardens Phase 5 - Wing 10 | about 4 km | Locked |
|---|
| Sobha Dream Gardens Phase 4 - Wing 1 And 2 | about 4 km | Locked |
|---|
| Sobha Dream Gardens Phase 3 - Wing 3 And 4 | about 4 km | Locked |
|---|
| Sai Kalyan Water Edge This project | This project is the point the others are measured from | 31 Dec 2027 | – | Not verified yet |
|---|---|---|---|---|
| 4square Park Sierra | about 1 km | 31 Dec 2029 | 8% (14 of 170) | Locked |
| Legacy Salvador | about 1.5 km | 31 Dec 2026 | 71% (119 of 167) | Locked |
| Cumins Sanctum | about 2 km | 31 Dec 2031 | 29% (32 of 112) | Locked |
| Assetz Soho & Sky Phase 1b | about 2 km | 31 Dec 2027 | 100% (120 of 120) | Locked |
| Assetz Soho & Sky | about 2.5 km | 30 Sep 2026 | 100% (114 of 114) | Locked |
| Godrej Aveline | about 3 km | 31 Mar 2031 | 91% (769 of 849) | Locked |
| Projects within 4 km, counted | 57 (57 with an approximate location) | |
|---|---|---|
| Flats in them | 17,042 | |
| Booked | 10,004 of 17,042 (59%) | |
| Unsold | 7,038 | |
| Booked a month, pooled | 271 flats | |
| Months to sell, pooled | 25 months |
Map of high-tension power lines, storm drains and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest government-flagged flood location | about 1.5 km, LBSnagar Yelahanka |
|---|
| Nearest storm drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Nearest lake, tank or pond | about 0.5 km, Jakkur Lake |
Map of storm drains, lakes and government-flagged flood locations within about 2 km of an approximate filed pin. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Ten-year July mean for this taluk: 32.6 m
Taluk average; not a reading at the site.
| Groundwater | Yelahanka taluk average, July 2023: 11.4 m below ground | |
|---|---|---|
| What it means | 10-20 m below ground, a class in CGWB's depth-to-water-level classes. In the pre-monsoon of 2025, 0 of 1 CGWB wells in Yelahanka taluk read in this class | |
| Through the year | January 2025: 3.8 m (1 well), Pre-monsoon 2025: 3.4 m (1 well), August 2025: 0.1 m (1 well), depth below ground of CGWB's monitoring wells in Yelahanka taluk (the median where there are several) | |
| Water supply, as filed | Self development |
| Schedule end | 15 Sep 2027 | |
|---|---|---|
| RERA completion date | 31 Dec 2027 | |
| Work began, as filed | 1 Jan 2021 |
Page 1
Page 1 of the specification sheet. The promoter filed this with the registration.
| Fire safety | Filed with the registration | |
|---|---|---|
| Environmental clearance | Filed with the registration |
| Escrow bank | Union Bank of India · Ghandhi Nagar | |
|---|---|---|
| Share of collections the promoter declared for escrow | 70% | |
| Registration at K-RERA | Withdrawn |
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
Map of drains, lakes, metro, high-tension lines and government-flagged flood locations within 3 km of the filed pin, with rings at 3 km. Approximate location: the filed pin, good to the neighbourhood, not the plot. The dashed ring is 1 km: of the approximate pins that could be checked against the surveyed land, nine in ten sat within it.
| Nearest drain | about 0.5 km, tertiary drain | |
|---|---|---|
| Metro, operational | about 9.5 km, Yeshwantpur | |
| Metro, under construction | about 2 km, Yelahanka |
| Kempegowda Airport | 25 | 16.5 |
| MG Road (CBD) | 17 | 12.5 |
| Manyata Tech Park | 6.5 | 5 |
| ITPL, Whitefield | 24 | 18 |
| Ecospace, Bellandur ORR | 29 | 19.5 |
| Electronic City Ph 1 | 37 | 28.5 |
| Landfill or waste transfer station | about 2 km | |
|---|---|---|
| Sewage treatment plant | about 0.5 km, named Sewage Treatment Plant on OpenStreetMap | |
| Quarry | about 2 km | |
| Crematorium | None within 3 km | |
| Prison | None within 3 km | |
| Electrical substation | about 1.5 km |