Overview
SAI KIRAN ENCLAVE
SAI ASHIRWAD CONSTRUCTION PRIVATE LIMITED · Patna
Units40
Booked11 of 40As of 2026-09-30
Construction progress85%As of 2026-09-30
Completion2026-05-15Proposed
Registered on2022-05-27
Valid to2026-05-15
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 2 unit types |
| Construction & progress | 4 progress details · 18 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 24 source links |
Registration
Registration
| Promoter | SAI ASHIRWAD CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP95525-3/90/R-1398/2022 | |
| Registered on | 2022-05-27 | |
| Valid to | 2026-05-15 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2026-05-15 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc. | ||
| Notice of Commencement | ||
| Environment Clearance | 2027-03-31 | STATE FIRE SERVICE, BIHAR, PATNA |
| Fire NOC | 2027-03-31 | PROVISIONAL FIRE PREVENTION AND FIRE SEFTY NO OBJECTION CERTIFICATE |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹96,21,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,467.76 | |
|---|---|---|
| Built-up (m²) | 3,663.26 | |
| FAR | 2.49 | |
| Towers | 1 | |
| Units | 40 | |
| Booked | 11 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| Convenience Store | 6 | SAI KIRAN ENCLAVE |
| 3 BHK | 34 | SAI KIRAN ENCLAVE |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 85% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2022-05-10 | |
| Proposed completion | 2026-05-15 |
Quarterly progress
| 2026-Q3 | 2026-10-18 | 85% | 11 |
| 2026-Q2 | 2026-07-19 | ||
| 2026-Q1 | 2026-04-15 | ||
| 2025-Q4 | 2026-01-14 | ||
| 2025-Q3 | 2025-10-13 | ||
| 2025-Q2 | 2025-08-20 | ||
| 2025-Q1 | 2025-04-15 | ||
| 2024-Q4 | 2025-01-11 | ||
| 2024-Q3 | 2024-10-15 | ||
| 2024-Q2 | 2024-07-14 | ||
| 2024-Q1 | 2024-07-25 | ||
| 2023-Q4 | 2024-07-25 | ||
| 2023-Q3 | 2024-07-25 | ||
| 2023-Q2 | 2024-07-25 | ||
| 2023-Q1 | 2023-04-14 | ||
| 2022-Q4 | 2023-01-12 | ||
| 2022-Q3 | 2022-10-10 | ||
| 2022-Q2 | 2022-07-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAI ASHIRWAD CONSTRUCTION PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC | |
| Other projects in this city pack | 2 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP02252022195525-3
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP02252022195525&ld=pan&pj=RERAP02252022195525-3&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP02252022195525-3
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Approved Layout Plan
- Area Development Plan
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-18
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-19
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-15
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-14
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-13
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-20
- Q4-Jan to Mar / 2024-2025 · 2025-04-15
- Q3-Oct to Dec / 2024-2025 · 2025-01-11
- Q2-Jul to Sep / 2024-2025 · 2024-10-15
- Q1-Apr to Jun / 2024-2025 · 2024-07-14
- Q4-Jan to Mar / 2023-2024 · 2024-07-25
- Q3-Oct to Dec / 2023-2024 · 2024-07-25
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-14
- Q3-Oct to Dec / 2022-2023 · 2023-01-12
- Q2-Jul to Sep / 2022-2023 · 2022-10-10
- Q1-Apr to Jun / 2022-2023 · 2022-07-15
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.
- Notice of Commencement
- 2026-Q2 · 2026-07-19
- 2026-Q1 · 2026-04-15
- 2025-Q4 · 2026-01-14
- 2025-Q3 · 2025-10-13
- 2025-Q2 · 2025-08-20
- 2025-Q1 · 2025-04-15
- 2024-Q4 · 2025-01-11
- 2024-Q3 · 2024-10-15
- 2024-Q2 · 2024-07-14
- 2024-Q1 · 2024-07-25
- 2023-Q4 · 2024-07-25
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-14
- 2022-Q4 · 2023-01-12
- 2022-Q3 · 2022-10-10
- 2022-Q2 · 2022-07-15