Sai Laxmi Complex

Maitreyee Mahanirman LLP · Patna
Units33
Booked12 of 33As of 2026-09-30
Construction progress57%As of 2026-09-30
Completion2024-04-17Proposed
Registered on2022-03-30
Valid to2024-04-17
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs1 cost head
Technical report
Site & area7 site details · 2 unit types
Construction & progress4 progress details · 18 quarters
Developer & finance
Developer4 developer details
The evidence
Sources32 documents · 24 source links

Registration

Registration

PromoterMaitreyee Mahanirman LLP
DistrictPatna
RegulatorRERA Bihar
Registration numberBRERAP05738-5/131/R-1318/2022
Registered on2022-03-30
Valid to2024-04-17
Project typeResidential/Group Housing
Status (as filed)New Project Launch
Proposed completion2024-04-17