Overview
SAI RAM GARDENS
SAI RAM PROJECTS · Visakhapatnam
Units20
Completion2023-06-29Proposed
Registered on2020-11-28
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 4 site details · 20 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 2 developer details |
| The evidence | |
| Sources | 24 documents · 10 source links |
Registration
Registration
| Promoter | SAI RAM PROJECTS | |
|---|---|---|
| District | Visakhapatnam | |
| Regulator | AP RERA | |
| Registration number | P03240201264 | |
| Registered on | 2020-11-28 | |
| Project type | Residential | |
| Status (as filed) | New Project | |
| Proposed completion | 2023-06-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Authority |
|---|---|---|---|
| Building / layout plan | 1086/1411/B/Z6/LAM/2020 | 2020-06-29 | Director,Town and Country Planning |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹84,01,000 | |
|---|---|---|
| Construction | ₹3,32,95,000 | |
| Total | ₹4,16,96,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 747.26 | |
|---|---|---|
| Built-up (m²) | 2,313.32 | |
| Towers | 1 | |
| Units | 20 |
Unit types
| 3 BHK | 79.75 | 1 | SAI RAM GARDENS | 1st (Ground Floor) |
| 3 BHK | 84.28 | 1 | SAI RAM GARDENS | 1st (Ground Floor) |
| 2 BHK | 59.81 | 1 | SAI RAM GARDENS | 1st (Ground Floor) |
| 2 BHK | 62.31 | 1 | SAI RAM GARDENS | 1st (Ground Floor) |
| 3 BHK | 79.75 | 1 | SAI RAM GARDENS | 2nd (First Floor) |
| 3 BHK | 84.28 | 1 | SAI RAM GARDENS | 2nd (First Floor) |
| 2 BHK | 59.81 | 1 | SAI RAM GARDENS | 2nd (First Floor) |
| 2 BHK | 62.31 | 1 | SAI RAM GARDENS | 2nd (First Floor) |
| 3 BHK | 79.75 | 1 | SAI RAM GARDENS | 3rd (Second Floor) |
| 3 BHK | 84.28 | 1 | SAI RAM GARDENS | 3rd (Second Floor) |
| 2 BHK | 59.81 | 1 | SAI RAM GARDENS | 3rd (Second Floor) |
| 2 BHK | 62.31 | 1 | SAI RAM GARDENS | 3rd (Second Floor) |
| 3 BHK | 79.75 | 1 | SAI RAM GARDENS | 4th (Third Floor) |
| 3 BHK | 84.28 | 1 | SAI RAM GARDENS | 4th (Third Floor) |
| 2 BHK | 59.81 | 1 | SAI RAM GARDENS | 4th (Third Floor) |
| 2 BHK | 62.31 | 1 | SAI RAM GARDENS | 4th (Third Floor) |
| 3 BHK | 79.75 | 1 | SAI RAM GARDENS | 5th (Fourth Floor) |
| 3 BHK | 84.28 | 1 | SAI RAM GARDENS | 5th (Fourth Floor) |
| 2 BHK | 59.81 | 1 | SAI RAM GARDENS | 5th (Fourth Floor) |
| 2 BHK | 62.31 | 1 | SAI RAM GARDENS | 5th (Fourth Floor) |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2020-08-20 | |
|---|---|---|
| Proposed completion | 2023-06-29 |
Quarterly progress
| 2020-Q4 | 2021-03-30 |
| 2021-Q3 | 2021-10-22 |
| 2021-Q4 | 2022-01-13 |
| 2022-Q1 | 2022-04-22 |
| 2022-Q2 | 2022-07-12 |
| 2022-Q3 | 2022-10-16 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAI RAM PROJECTS | |
|---|---|---|
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.ap.gov.in/RERA/Views/GeoMap.aspx
- https://rera.ap.gov.in/RERA/Views/Project.aspx??enc=mUX5JvffTObOCE+6xFBEFZtr4yFJY86mVgp7uZCOq9snkqQQS2sqwQ4Lm90HeK+iIq0UUlAWt7uZAlI/POlwvibEkPsFbvshgKUsFvFaSpzfUFp7QFhAfp3NFtv5Ch+L
- https://rera.ap.gov.in/RERA/Views/Reports/ApprovedProjects.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/DwellingUnitsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjExpectedDateofCompletion.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/ProjectClosureReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QprProjectsReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/QuarterlyReport.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/SoldInformation.aspx
- https://rera.ap.gov.in/RERA/Views/Reports/TotalBuildupArea.aspx
- Promoter registration certificate
- Promoter GST certificate
- Litigation details
- Modified plan
- Architect certificate
- Board resolution
- 1.Income Tax Return Acknowledgement of Preceding Year 1
- 2. Income Tax Return Acknowledgement of Preceding Year 2
- 3.Income Tax Return Acknowledgement of Preceding Year 3
- 4.Balance Sheet
- 10. Detailed site plan showing the measurements as on ground including diagonals, Latitude and Longitude at end points of the project site
- 15. Details of the cases pending before the Authorities or in Courts of Law and their current status along with the copies of the orders issued
- 16. Copy of the plan and proceedings issued by the competent Authority for approval of plans
- 17. Approved plan / list of amenities proposed in the site
- 18. NOC's issued by Authority
- 19. Detailed technical specifications of the construction if the buildings and facilities proposed in the project including brand specifications details of fixtures and fittings
- 20. Full address of the proposed development project along with the land mark nearby and a location plan/ Topo plan drawn to a scale
- 21. Licenses/Enrolment form of Civil Contractors, or turnkey contractor, or EPC Contractors.
- 25.Licenses/Enrolment form of Chartered Accountant or firm or company
- 26.Detailed estimate of the expenditure for construction of the building
- 27. Statement of source of funds for construction of project
- 29.Proforma of the Allotment Letter proposed to be signed with the Allottee
- 32.Structural Stability Certificate duly issued by Certified Structural Consultant/Engineer along with the details of parameters followed for verification of structural stability *
- APRERA CERTIFICATE