Overview
Sai Shanti Enclave
Aastik Buildtech Private Limited · Patna
Units51
Completion2020-03-31Proposed
Registered on2018-09-27
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 15 unit types |
| Construction & progress | 2 progress details · 10 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 23 documents · 16 source links |
Registration
Registration
| Promoter | Aastik Buildtech Private Limited | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00278-1/247/R-193/2018 | |
| Registered on | 2018-09-27 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2020-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹5,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,100.23 | |
|---|---|---|
| Built-up (m²) | 4,156.04 | |
| FAR | 1.97 | |
| Towers | 1 | |
| Units | 51 |
Unit types
| 2 BHK | 6 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 2 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 6 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 2 BHK | 3 | Sai Shanti Enclave |
| 2 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
| 3 BHK | 3 | Sai Shanti Enclave |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-09-24 | |
|---|---|---|
| Proposed completion | 2020-03-31 |
Quarterly progress
| 2021-Q2 | 2021-08-19 |
| 2021-Q1 | 2021-08-15 |
| 2020-Q4 | 2021-04-30 |
| 2020-Q3 | 2020-12-06 |
| 2020-Q2 | 2020-09-22 |
| 2020-Q1 | 2021-07-06 |
| 2019-Q4 | 2020-01-31 |
| 2019-Q3 | 2019-10-31 |
| 2019-Q2 | 2019-08-01 |
| 2019-Q1 | 2019-04-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Aastik Buildtech Private Limited | |
|---|---|---|
| Type | Company | |
| Escrow bank | FEDERAL BANK OF INDIA | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP234201800278-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP234201800278-1
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2021-2022 · 2021-08-19
- Q4-Jan to Mar / 2020-2021 · 2021-08-15
- Q3-Oct to Dec / 2020-2021 · 2021-04-30
- Q2-Jul to Sep / 2020-2021 · 2020-12-06
- Q1-Apr to Jun / 2020-2021 · 2020-09-22
- Q4-Jan to Mar / 2019-2020 · 2021-07-06
- Q3-Oct to Dec / 2019-2020 · 2020-01-31
- Q2-Jul to Sep / 2019-2020 · 2019-10-31
- Q1-Apr to Jun / 2019-2020 · 2019-08-01
- Q4-Jan to Mar / 2018-2019 · 2019-04-30
- Project Photogragh · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2021-Q2 · 2021-08-19
- 2021-Q1 · 2021-08-15
- 2020-Q4 · 2021-04-30
- 2020-Q3 · 2020-12-06
- 2020-Q2 · 2020-09-22
- 2020-Q1 · 2021-07-06
- 2019-Q4 · 2020-01-31
- 2019-Q3 · 2019-10-31
- 2019-Q2 · 2019-08-01
- 2019-Q1 · 2019-04-30