Overview
SAI VILLAS CLASSIC PHASE - II
BHARDWAJ PROMOTERS & BUILDERS · DURG
Units76
Booked42 of 76As of 2026-06-30
Construction progress61%As of 2026-06-30
Completion2028-02-29Revised · Proposed 2027-10-31
Registered on2022-12-15
Approvals4
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Contract & costs | 2 cost heads · 15 quarters |
| Technical report | |
| Site & area | 3 site details · 76 unit types |
| Construction & progress | 4 progress details · 15 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 96 documents · 7 source links |
Registration
Registration
| Promoter | BHARDWAJ PROMOTERS & BUILDERS | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA151222001562 | |
| Registered on | 2022-12-15 | |
| Project type | Group Housing | |
| Status (as filed) | New | |
| Proposed completion | 2027-10-31 | |
| Revised completion | 2028-02-29 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹6,88,06,000 | |
|---|---|---|
| Construction | ₹28,21,55,000 |
Quarterly money flows
| 2022-Q4 | ₹0 |
| 2023-Q1 | ₹0 |
| 2023-Q2 | ₹111 |
| 2023-Q3 | ₹20,099 |
| 2023-Q4 | ₹2,00,928 |
| 2024-Q1 | ₹14,01,626 |
| 2024-Q2 | ₹622 |
| 2024-Q3 | ₹86 |
| 2024-Q4 | ₹73 |
| 2025-Q1 | ₹21,73,509.7 |
| 2025-Q2 | ₹7,00,161 |
| 2025-Q3 | ₹63 |
| 2025-Q4 | ₹88,900 |
| 2026-Q1 | ₹540 |
| 2026-Q2 | ₹96 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 76 | |
|---|---|---|
| Booked | 42 | |
| Booked as of | 2026-06-30 |
Unit types
| 3BHK | 103.78 | 1 | 0 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 137.65 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 1 |
| 3BHK | 103.78 | 1 | 0 |
| 3BHK | 105.75 | 1 | 1 |
| 3BHK | 105.75 | 1 | 1 |
| 3BHK | 105.75 | 1 | 1 |
| 3BHK | 93.2 | 1 | 1 |
| 3BHK | 102.14 | 1 | 1 |
| 3BHK | 106.28 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 122.28 | 1 | 0 |
| 3BHK | 106.97 | 1 | 0 |
| 3BHK | 106.23 | 1 | 0 |
| 3BHK | 106.23 | 1 | 0 |
| 3BHK | 106.23 | 1 | 0 |
| 3BHK | 106.23 | 1 | 0 |
| 3BHK | 106.23 | 1 | 0 |
| 3BHK | 105.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 101.75 | 1 | 0 |
| 3BHK | 127.92 | 1 | 0 |
| 3BHK | 129.72 | 1 | 1 |
| 3BHK | 126.49 | 1 | 1 |
| 3BHK | 126.49 | 1 | 1 |
| 3BHK | 127.49 | 1 | 1 |
| 3BHK | 127.49 | 1 | 0 |
| 3BHK | 127.49 | 1 | 1 |
| 3BHK | 141.09 | 1 | 1 |
| 3BHK | 142.96 | 1 | 1 |
| 3BHK | 132.67 | 1 | 1 |
| 3BHK | 132.67 | 1 | 1 |
| 3BHK | 132.67 | 1 | 1 |
| 3BHK | 132.16 | 1 | 1 |
| 3BHK | 132.16 | 1 | 0 |
| 3BHK | 134.64 | 1 | 0 |
| 3BHK | 134.27 | 1 | 0 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 102.3 | 1 | 1 |
| 3BHK | 102.3 | 1 | 1 |
| 3BHK | 102.3 | 1 | 1 |
| 3BHK | 141.09 | 1 | 1 |
| 3BHK | 134.88 | 1 | 0 |
| 3BHK | 122.66 | 1 | 1 |
| 3BHK | 122.66 | 1 | 1 |
| 3BHK | 122.66 | 1 | 0 |
| 3BHK | 127.96 | 1 | 0 |
| 3BHK | 122.81 | 1 | 1 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 101.75 | 1 | 1 |
| 3BHK | 128.88 | 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 61% | |
|---|---|---|
| As of | 2026-06-30 | |
| Proposed completion | 2027-10-31 | |
| Revised completion | 2028-02-29 |
Quarterly progress
| 2022-Q4 | 0% |
| 2023-Q1 | 0% |
| 2023-Q2 | 1% |
| 2023-Q3 | 11% |
| 2023-Q4 | 15% |
| 2024-Q1 | 16% |
| 2024-Q2 | 26% |
| 2024-Q3 | 27% |
| 2024-Q4 | 29% |
| 2025-Q1 | 47% |
| 2025-Q2 | 52% |
| 2025-Q3 | 53% |
| 2025-Q4 | 57% |
| 2026-Q1 | 59% |
| 2026-Q2 | 61% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BHARDWAJ PROMOTERS & BUILDERS | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 6 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTkxMw==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities