Overview
Sai Yash Recidencey
SUKRITI STRUCTURES PVT.LTD · Lucknow
Units72
Completion2022-02-14Revised · Proposed 2021-08-15
Registered on2017-10-23
Valid to2022-02-14
Approvals3
Complaints3As of 2026-10-29
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 3 project complaints · 3 promoter complaints |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 4 site details · 72 unit types |
| Construction & progress | 3 progress details · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 6 documents · 7 source links |
Registration
Registration
| Promoter | SUKRITI STRUCTURES PVT.LTD | |
|---|---|---|
| District | Lucknow | |
| Regulator | UP RERA | |
| Registration number | UPRERAPRJ13687 | |
| Registered on | 2017-10-23 | |
| Valid to | 2022-02-14 | |
| Project type | Residential | |
| Status (as filed) | Registered Projects | |
| Proposed completion | 2021-08-15 | |
| Revised completion | 2022-02-14 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Original permit | PATRANK 27/NAKSHA/NEE.VEE/JILA PANCHAYAT/2012-2013 | 2012-07-03 | 2017-07-02 | Any Other Competent Authority |
| Original permit | PATRANK 27/NAKSHA/NEE.VEE/JILA PANCHAYAT/2012-2013 | 2012-07-03 | 2017-07-02 | Any Other Competent Authority |
| Revalidated permit | PATRANK 27/NAKSHA/NEE.VEE/JILA PANCHAYAT/2012-2013 | 2012-07-03 | 2018-07-02 | Any Other Competent Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 3 | |
|---|---|---|
| Promoter | 3 | |
| As of | 2026-10-29 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹1,66,25,40,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 15,114 | |
|---|---|---|
| Towers | 1 | |
| Maximum floors | 9 | |
| Units | 72 |
Unit types
| 3 BHK | 109.59 | 1 | TOWER- T2 | 1 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 1 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 1 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 1 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 1 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 1 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 1 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 1 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 2 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 2 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 2 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 2 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 2 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 2 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 2 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 2 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 3 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 3 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 3 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 3 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 3 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 3 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 3 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 3 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 4 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 4 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 4 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 4 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 4 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 4 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 4 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 4 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 5 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 5 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 5 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 5 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 5 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 5 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 5 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 5 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 6 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 6 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 6 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 6 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 6 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 6 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 6 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 6 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 7 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 7 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 7 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 7 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 7 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 7 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 7 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 7 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 8 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 8 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 8 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 8 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 8 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 8 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 8 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 8 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 9 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 9 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 9 |
| 3 BHK | 109.77 | 1 | TOWER- T2 | 9 |
| 2 BHK | 87.84 | 1 | TOWER- T2 | 9 |
| 3 BHK | 109.59 | 1 | TOWER- T2 | 9 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 9 |
| 3 BHK | 109.69 | 1 | TOWER- T2 | 9 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-08-16 | |
|---|---|---|
| Proposed completion | 2021-08-15 | |
| Revised completion | 2022-02-14 |
Extensions
| Valid to | Reason |
|---|---|
| 2022-02-14 | Six months extension in view of force majeure caused by covid-19 pandemic |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SUKRITI STRUCTURES PVT.LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | Corporation Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://up-rera.in/Projectsummary?UI0aPA1ISD=b1OGYq4k+Kc=&hfFlag=GL34ZTSSjlw=&NPJ6RAme=+iRW3NmMDBtyr1WqfKkvKsiz9kOcuFoP&PaURJEMAN4=ZL9MNERkNdZzHFBIJ9btJg==&IRSAHEB=D6PY3lyims8=
- https://up-rera.in/QPRDOCS
- https://up-rera.in/WebService1.asmx/loadApartmentTransaction_ForViewProject
- https://up-rera.in/frm_allprojectdistrictwise.aspx?districtname=LUCKNOW
- https://up-rera.in/projects
- https://up-rera.in/viewprojects
- https://up-rera.in/viewtarget.aspx?id=b1OGYq4k%2BKc=
- ARCHITECT CERTIFICATE · 2021-10-21 · Sign in to download
- ENGINEERS CERTIFICATE · 2021-10-21 · Sign in to download
- Commencement Certificate · 2017-10-18
- Sanctioned Layout Plan (Of Entire Project) · 2017-10-18
- Sanctioned Layout Plan (Of Entire Project) · 2017-10-18
- Sanctioned Layout Plan (Of Entire Project) · 2017-10-18