DOSLAssam Workspace

Overview

SAILAJA'S PARADISE

SAILAJA CONSTRUCTION · ADP ROAD
Units30
Completion2028-03-01Proposed
Registered on2023-03-02
Valid to2028-03-01
Approvals5

Sections

Property title & search report
Approvals5 approvals
Contract & costs3 cost heads · 14 quarters
Technical report
Site & area2 site details · 4 unit types
Construction & progress2 progress details · 14 quarters
Developer & finance
Developer2 developer details
The evidence
Sources97 documents · 6 source links

Registration

Registration

PromoterSAILAJA CONSTRUCTION
DistrictNAGAON
LocalityADP ROAD
RegulatorRERA Assam
Registration numberRERAA NN 128 OF 2023-2024
Registered on2023-03-02
Valid to2028-03-01
Status (as filed)Ongoing Projects
Proposed completion2028-03-01