Overview
SAINATH COMMERCIAL
BIRENDRA KUMAR LALA · BASTAR
Units58
Construction progress100%As of 2018-09-30
Completion2018-12-31Proposed
Registered on2018-09-05
Cases2
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 2 cases |
| Contract & costs | 2 cost heads · 1 quarter |
| Technical report | |
| Site & area | 2 site details · 1 unit type |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 5 documents · 7 source links |
Registration
Registration
| Promoter | BIRENDRA KUMAR LALA | |
|---|---|---|
| District | BASTAR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA050918000749 | |
| Registered on | 2018-09-05 | |
| Project type | Plotted Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2018-12-31 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-PRO-2025-02822 | CG RERA | Complaint | Disposed | 2025-07-07 |
| M-COM-2019-00592 | CG RERA | Complaint | Disposed | 2021-10-20 |
Complaints & cases
| Cases | 2 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,55,90,000 | |
|---|---|---|
| Construction | ₹5,50,87,22,000 |
Quarterly money flows
| Quarter | Escrow balance |
|---|---|
| 2018-Q3 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 58 | |
|---|---|---|
| Booked as of | 2018-09-30 |
Unit types
| Type | Units | Booked |
|---|---|---|
| Commercial | 58 | 58 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2018-09-30 | |
| Proposed completion | 2018-12-31 |
Quarterly progress
| Quarter | Progress |
|---|---|
| 2018-Q3 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | BIRENDRA KUMAR LALA | |
|---|---|---|
| Type | Individual | |
| Escrow bank | Punjab and Sind Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=ODQz
- https://rera.cgstate.gov.in/cause_list.aspx
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Final order · 2025-07-07 · Sign in to download
- Final order · 2021-10-20 · Sign in to download
- M-PRO-2025-02822 · Sign in to download
- M-COM-2019-00592 · Sign in to download