Overview
SALMA RESIDENCY
PEACE S SQUARE BUILDTECH · Patna
Units16
Booked10 of 16As of 2026-09-30
Construction progress100%As of 2026-09-30
Completion2028-06-30Proposed
Registered on2025-07-15
Valid to2028-06-30
Approvals8
Sections
| Property title & search report | |
|---|---|
| Approvals | 8 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 1 unit type |
| Construction & progress | 4 progress details · 5 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 18 documents · 11 source links |
Registration
Registration
| Promoter | PEACE S SQUARE BUILDTECH | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP188228070725300628E00 | |
| Registered on | 2025-07-15 | |
| Valid to | 2028-06-30 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2028-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | PATNA NAGAR NIGAN | |
| Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc. | ||
| Notice of Commencement in form X | ||
| Environment Clearance | 2026-10-26 | no |
| Fire NOC | 2027-12-31 | yes |
| Airport NOC | 2027-12-31 | yes |
| Water Supply Permission | 2027-10-26 | yes |
| Other approval | 2026-10-26 | no |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹1,32,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 485.62 | |
|---|---|---|
| Built-up (m²) | 1,128.48 | |
| FAR | 2 | |
| Towers | 1 | |
| Units | 16 | |
| Booked | 10 | |
| Booked as of | 2026-09-30 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 16 | SALMA RESIDENCY |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2026-09-30 | |
| Start | 2025-02-20 | |
| Proposed completion | 2028-06-30 |
Quarterly progress
| 2026-Q3 | 2026-10-26 | 100% | 10 |
| 2026-Q2 | 2026-07-29 | ||
| 2026-Q1 | 2026-04-17 | ||
| 2025-Q4 | 2026-01-30 | ||
| 2025-Q3 | 2025-10-16 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PEACE S SQUARE BUILDTECH | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Kotak Mahindra | |
| Other projects in this city pack | 6 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP06182019184906-7
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP06182019184906&ld=pan&pj=RERAP06182019184906-7&f=2026-2027&q=2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP06182019184906-7
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q2 (Jul - Sep) / 2026-2027 · 2026-10-26
- Quarterly Progress Image · 2025-10-16
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-29
- Q4 (Jan - Mar) / 2025-2026 · 2026-04-17
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-30
- Q2 (Jul - Sep) / 2025-2026 · 2025-10-16
- Project Photogragh · Sign in to download
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Any other Project related documents enviromental clearance, fire NOCs/AAI, IT Return/Environmental clearance etc.
- Notice of Commencement in form X
- 2026-Q2 · 2026-07-29
- 2026-Q1 · 2026-04-17
- 2025-Q4 · 2026-01-30
- 2025-Q3 · 2025-10-16