DOSLDelhi NCR Workspace

Overview

SAMSARA IVANA

ADANI BRAHMA SYNERGY PRIVATE LIMITED · Gurugram
Units192
Completion2029-03-31Proposed
Registered on2024-12-18
Valid to2029-06-30
Approvals4

Sections

Property title & search report
Approvals4 approvals
Contract & costs3 cost heads
Technical report
Site & area2 site details · 3 unit types
Construction & progress2 progress details
Developer & finance
Developer4 developer details
The evidence
Sources51 documents · 3 source links

Registration

Registration

PromoterADANI BRAHMA SYNERGY PRIVATE LIMITED
DistrictGurugram
RegulatorHRERA Gurugram
Registration numberGGM/896/628/2024/123 DATED 18.12.2024
Registered on2024-12-18
Valid to2029-06-30
Status (as filed)Registered
Proposed completion2029-03-31