Overview
SANJEEVNI GREEN VIHAR PHASE-I
MS SANJEEVNI BUILDHOME · Jaipur
Units29
Booked20 of 29As of 2025-09-30
Completion2025-02-28Revised · Proposed 2024-09-02
Registered on2024-10-28
Valid to2026-06-28
Sections
| Property title & search report | |
|---|---|
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 6 unit types |
| Construction & progress | 3 progress details · 1 quarter · 2 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 29 documents · 7 source links |
Registration
Registration
| Promoter | MS SANJEEVNI BUILDHOME | |
|---|---|---|
| District | Jaipur | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2024/3344 | |
| Registered on | 2024-10-28 | |
| Valid to | 2026-06-28 | |
| Project type | Plotted | |
| Status (as filed) | LAPSED | |
| Proposed completion | 2024-09-02 | |
| Revised completion | 2025-02-28 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | LAPSED | |
|---|---|---|
| Valid to | 2026-06-28 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹73,95,412 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹1,79,60,287 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2025-Q3 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 8,027 | |
|---|---|---|
| Built-up (m²) | 3,533.43 | |
| Towers | 29 | |
| Units | 29 | |
| Booked | 20 | |
| Booked as of | 2025-09-30 |
Unit types
| Plot No. 14-16, 33-40, 49-53, 74-78 | 21 | 0 |
| Plot No. 17, 32, 54, 73 | 4 | 0 |
| Plot No. 48 | 1 | 0 |
| Plot No. 79 | 1 | 0 |
| Plot no. 86 | 1 | 0 |
| Plot No. 85 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-09-02 | |
|---|---|---|
| Proposed completion | 2024-09-02 | |
| Revised completion | 2025-02-28 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2025-Q3 | 2025-11-30 | 20 |
Extensions
| Valid to |
|---|
| 2026-02-28 |
| 2026-06-28 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | MS SANJEEVNI BUILDHOME | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | AU SMALL FINANCE BANK | |
| Other projects in this city pack | 13 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=SziMfAj0D1faSIzL7Jmckg
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/SziMfAj0D1faSIzL7Jmckg
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=SziMfAj0D1faSIzL7Jmckg%3D%3D&QuarterIdEnc=s291bsdE%2FxcYMFPaLLqdrQ%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=JqH3hMiWiM4%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Gantt Charts Or Milestone Charts And Project Schedule · Sign in to download
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- FormFUploadedPathString · Sign in to download
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- Bankaffidavit · Sign in to download
- SitePlanPath · 2024-09-25
- LayoutPlanPath · 2024-09-25
- SitePlanPath · 2024-09-25
- SitePlanPath · 2024-09-25
- SitePlanPath · 2024-09-25
- SitePlanPath · 2024-09-25
- Site_Plan_Doc_Sanctioned
- RCertificate
- MCAdata · Sign in to download
- LLPDeed · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2025-10-28 · Sign in to download
- R2_UploadDoc · 2025-09-30 · Sign in to download
- R3_UploadedPath · 2025-03-31 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download
- Extension order · Sign in to download