Overview
SANTUR AZALEA
SANTUR BUILDERS PRIVATE LIMITED · Gurugram
Units138
Completion2029-06-30Proposed
Registered on2025-01-27
Valid to2029-06-30
Approvals6
Sections
| Property title & search report | |
|---|---|
| Approvals | 6 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 2 site details · 2 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 34 documents · 3 source links |
Registration
Registration
| Promoter | SANTUR BUILDERS PRIVATE LIMITED | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/905/637/2025/08 DATED 27.01.2025 | |
| Registered on | 2025-01-27 | |
| Valid to | 2029-06-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2029-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 197 of 2022 | Town & Country Planning Department | |
| Layout Plan | 2024-11-21 | ||
| Building Plan | |||
| I. SITE PLAN | 2022-12-01 | ||
| II. LICENCE | 2022-11-29 | ||
| III. ZONING | 2023-09-19 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹56,82,02,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹1,28,83,70,000 |
Site & area
What does the land measure?
Site & area
Site & area
| FAR | 0 | |
|---|---|---|
| Units | 138 |
Unit types
| Type | Carpet (m²) | Units |
|---|---|---|
| Plot | 138 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2025-02-01 | |
|---|---|---|
| Proposed completion | 2029-06-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SANTUR BUILDERS PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | ICICI BANK LIMITED | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2974
- https://nominatim.openstreetmap.org/search?q=sector+2%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2025-01-27
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2024-06-05 · Sign in to download
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2024-05-31
- DEMARCATION PLAN · 2024-05-31
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2024-05-31
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2024-05-31
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2024-05-31
- ZONING PLAN · 2024-05-31
- DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. · 2024-06-04 · Sign in to download
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2024-06-05 · Sign in to download
- APPROVAL OF REVISED LAYOUT PLAN · 2025-01-31
- STORM WATER DRAINAGE SCHEME · 2025-01-31 · Sign in to download
- APPROVAL OF SINGLE LINE DIAGRAM · 2025-01-31
- ROAD PLAN · 2025-01-31
- APPROVAL OF ZONING_LETTER · 2025-01-31
- APPROVED_COMMUNITY_ZONING · 2025-01-31 · Sign in to download
- NOC NON FOREST LAND · 2025-01-31
- APPROVED_COMMERCIAL_ZONING · 2025-01-31 · Sign in to download
- APPROVAL OF BUILDING PLAN FOR TEMPORARY SITE OFFICE · 2025-01-31
- SUPPLY OF DRINKING WATER REQUEST · 2025-01-31 · Sign in to download
- APPROVAL OF REVISED BUILDING PLANS · 2025-01-31
- CA CERTIFICATE-NO DUES · 2025-01-31 · Sign in to download
- APPROVAL OF ELECTRICAL LOAD · 2025-01-31
- NOC AAI · 2025-01-31
- CLARIFICATION REGARDING APPLICABILITY OF FOREST LAWS ON NON FOREST LAND · 2025-01-31 · Sign in to download
- LOI-9.394 ACRES · 2025-01-31 · Sign in to download
- GIFT DEED · 2025-01-31 · Sign in to download
- NOC ACCESS PERMISSION FROM NHAI · 2025-01-31
- REVISED_APPROVED_ZONING · 2025-01-31 · Sign in to download
- APPROVED SERVICE ESTIMATE PLAN · 2025-01-31
- SERVICE ESTIMATE · 2025-01-31 · Sign in to download
- SEWERAGE SCHEME · 2025-01-31 · Sign in to download
- WATER SUPPLY SCHEME · 2025-01-31 · Sign in to download
- CA CERTIFICATE_COST · 2025-01-31 · Sign in to download