Overview
SAPPHIRE EIGHTYTHREE
SAPHIRE LANDCRAFT PVT LTD · Gurugram
Units1
Completion2022-12-31Revised · Proposed 2022-12-31
Registered on2017-12-09
Valid to2018-03-31
Approvals4
Cases6
Sections
| Property title & search report | |
|---|---|
| Approvals | 4 approvals |
| Disputes & cases | 6 cases |
| Contract & costs | 2 cost heads |
| Technical report | |
| Site & area | 3 site details · 1 unit type |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 8 documents · 4 source links |
Registration
Registration
| Promoter | SAPHIRE LANDCRAFT PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | 388 OF 2017 DATED 09.12.2017 | |
| Registered on | 2017-12-09 | |
| Valid to | 2018-03-31 | |
| Status (as filed) | Registered | |
| Proposed completion | 2022-12-31 | |
| Revised completion | 2022-12-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 129 of 31-12-2012 | Town & Country Planning Department | |
| Layout Plan | 2013-05-17 | ||
| Building Plan | 2013-05-17 | ||
| I. OCCUPATION CERTIFICATE | 2018-05-18 |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| RERA-GRG-3039-2022 | HRERA Gurugram | |
| RERA-GRG-5324-2019 | HRERA Gurugram | Pending |
| RERA-GRG-3840-2022 | HRERA Gurugram | Pending |
| RERA-GRG-3838-2022 | HRERA Gurugram | Pending |
| RERA-GRG-3553-2022 | HRERA Gurugram | Pending |
| RERA-GRG-4964-2022 | HRERA Gurugram | Pending |
Complaints & cases
| Cases | 6 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,23,32,20,02,00,000 | |
|---|---|---|
| Construction | ₹7,60,43,53,21,00,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 14,253.005 | |
|---|---|---|
| FAR | 1.75 | |
| Units | 1 |
Unit types
| Type | Units |
|---|---|
| 1 | 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Proposed completion | 2022-12-31 | |
|---|---|---|
| Revised completion | 2022-12-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SAPHIRE LANDCRAFT PVT LTD | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/assistancecontrol/view_monitoring_cases/Mzg4IG9mIDIwMTcgREFURUQgMDkuMTIuMjAxNw==
- https://haryanarera.gov.in/view_project/project_preview_open/1201
- https://nominatim.openstreetmap.org/search?q=sector+83%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2017-12-09
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2020-02-11 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2020-02-11
- DEMARCATION PLAN · 2020-02-11
- ZONING PLAN · 2020-02-11
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2020-02-11
- ANNEXURE- DETAILS OF THE PLOTS/APARTMENTS IN THE PROJECT · 2021-03-10 · Sign in to download
- OC uploaded · 2023-08-08 · Sign in to download