DOSLChhattisgarh Workspace

Overview

SAPPHIRE EMPERIA PHASE -3 BLOCK "D"

OM CONSTRUCTION · RAIPUR
Units42
Booked30 of 42As of 2021-09-30
Construction progress100%As of 2021-09-30
Completion2022-09-30Revised · Proposed 2021-12-31
Registered on2018-08-08
Approvals1

Sections

Property title & search report
Approvals1 approval
Contract & costs2 cost heads · 13 quarters
Technical report
Site & area3 site details · 9 unit types
Construction & progress4 progress details · 13 quarters
Developer & finance
Developer4 developer details
The evidence
Sources99 documents · 4 source links

Registration

Registration

PromoterOM CONSTRUCTION
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA080818000669
Registered on2018-08-08
Project typeMixed Development
Status (as filed)Ongoing
Proposed completion2021-12-31
Revised completion2022-09-30