Overview
SAPPHIRE EMPERIA PHASE -4 BLOCK "E"
OM CONSTRUCTION · RAIPUR
Units84
Booked40 of 84As of 2025-06-30
Construction progress100%As of 2025-06-30
Completion2025-09-30Revised · Proposed 2023-12-31
Registered on2018-08-08
Approvals3
Cases1
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 1 case |
| Contract & costs | 2 cost heads · 28 quarters |
| Technical report | |
| Site & area | 3 site details · 84 unit types |
| Construction & progress | 4 progress details · 28 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 200 documents · 9 source links |
Registration
Registration
| Promoter | OM CONSTRUCTION | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA080818000668 | |
| Registered on | 2018-08-08 | |
| Project type | Mixed Development | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2023-12-31 | |
| Revised completion | 2025-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind | Status | Decided on |
|---|---|---|---|---|
| M-COM-2023-02072 | CG RERA | Complaint | Disposed | 2024-01-05 |
Complaints & cases
| Cases | 1 |
|---|
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹97,99,000 | |
|---|---|---|
| Construction | ₹18,54,31,000 |
Quarterly money flows
| 2018-Q3 | ₹0 |
| 2018-Q4 | ₹0 |
| 2019-Q1 | ₹14,776 |
| 2019-Q2 | ₹14,664 |
| 2019-Q3 | ₹14,552 |
| 2019-Q4 | ₹14,534 |
| 2020-Q1 | ₹14,440 |
| 2020-Q2 | ₹14,186 |
| 2020-Q3 | ₹13,933 |
| 2020-Q4 | ₹13,679 |
| 2021-Q1 | ₹13,425 |
| 2021-Q2 | ₹13,408 |
| 2021-Q3 | ₹13,390 |
| 2021-Q4 | ₹13,372 |
| 2022-Q1 | ₹13,354 |
| 2022-Q2 | ₹13,336 |
| 2022-Q3 | ₹13,319 |
| 2022-Q4 | ₹13,301 |
| 2023-Q1 | ₹13,284 |
| 2023-Q2 | ₹13,284 |
| 2023-Q3 | ₹13,282 |
| 2023-Q4 | ₹13,280 |
| 2024-Q1 | ₹8,93,177 |
| 2024-Q2 | ₹23,42,273 |
| 2024-Q3 | ₹3,53,261 |
| 2024-Q4 | ₹10,253 |
| 2025-Q1 | ₹11,931 |
| 2025-Q2 | ₹2,90,873 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 84 | |
|---|---|---|
| Booked | 40 | |
| Booked as of | 2025-06-30 |
Unit types
| 3BHK | 91.56 | 1 | 1 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 0 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 85.35 | 1 | 0 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 108.49 | 1 | 0 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 85.35 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 108.49 | 1 | 1 |
| 3BHK | 142.87 | 1 | 1 |
| 3BHK | 85.35 | 1 | 1 |
| COMMERCIAL | 99.49 | 1 | 1 |
| COMMERCIAL | 75.03 | 1 | 1 |
| COMMERCIAL | 119.69 | 1 | 1 |
| COMMERCIAL | 54.81 | 1 | 0 |
| COMMERCIAL | 43.72 | 1 | 0 |
| COMMERCIAL | 41.98 | 1 | 0 |
| COMMERCIAL | 68.43 | 1 | 0 |
| COMMERCIAL | 66.11 | 1 | 0 |
| COMMERCIAL | 54.18 | 1 | 0 |
| COMMERCIAL | 13.15 | 1 | 0 |
| COMMERCIAL | 13.07 | 1 | 0 |
| COMMERCIAL | 11.42 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2025-06-30 | |
| Proposed completion | 2023-12-31 | |
| Revised completion | 2025-09-30 |
Quarterly progress
| 2018-Q3 | 37% |
| 2018-Q4 | 37% |
| 2019-Q1 | 37% |
| 2019-Q2 | 37% |
| 2019-Q3 | 37% |
| 2019-Q4 | 37% |
| 2020-Q1 | 37% |
| 2020-Q2 | 37% |
| 2020-Q3 | 37% |
| 2020-Q4 | 37% |
| 2021-Q1 | 37% |
| 2021-Q2 | 37% |
| 2021-Q3 | 37% |
| 2021-Q4 | 37% |
| 2022-Q1 | 37% |
| 2022-Q2 | 37% |
| 2022-Q3 | 39% |
| 2022-Q4 | 46% |
| 2023-Q1 | 47% |
| 2023-Q2 | 50% |
| 2023-Q3 | 54% |
| 2023-Q4 | 57% |
| 2024-Q1 | 62% |
| 2024-Q2 | 69% |
| 2024-Q3 | 73% |
| 2024-Q4 | 85% |
| 2025-Q1 | 85% |
| 2025-Q2 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | OM CONSTRUCTION | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 8 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_delay_not_extended.aspx
- https://rera.cgstate.gov.in/ComplaintDocs_final_order_section_all.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=NzU4
- https://rera.cgstate.gov.in/cause_list.aspx
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Building Plan
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Agent Details · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Brouchre · Sign in to download
- Final order · 2024-01-05 · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities
- M-COM-2023-02072 · Sign in to download