DOSLChhattisgarh Workspace

Overview

SAPPHIRE INFRATECH SG- PHASE-1(J)

SAPPHIRE INFRATECH · RAIPUR
Units159
Booked38 of 159As of 2023-06-30
Construction progress100%As of 2023-06-30
Completion2025-06-30Revised · Proposed 2025-03-31
Registered on2021-03-26
Approvals1

Sections

Property title & search report
Approvals1 approval
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area3 site details · 25 unit types
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer4 developer details
The evidence
Sources73 documents · 4 source links

Registration

Registration

PromoterSAPPHIRE INFRATECH
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA260321001214
Registered on2021-03-26
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2025-03-31
Revised completion2025-06-30