SAPPHIRE INFRATECH SG PHASE- 1P

SAPPHIRE INFRATECH · RAIPUR
Units197
Booked65 of 197As of 2025-12-31
Construction progress100%As of 2025-12-31
Completion2027-10-09Revised · Proposed 2027-06-09
Registered on2022-08-22
Approvals4

Sections

Property title & search report
Approvals4 approvals
Contract & costs2 cost heads · 14 quarters
Technical report
Site & area3 site details · 197 unit types
Construction & progress4 progress details · 14 quarters
Developer & finance
Developer3 developer details
The evidence
Sources98 documents · 7 source links

Registration

Registration

PromoterSAPPHIRE INFRATECH
DistrictRAIPUR
RegulatorCG RERA
Registration numberPCGRERA220822001509
Registered on2022-08-22
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2027-06-09
Revised completion2027-10-09