Overview
SB CENTRUM PHASE II
SABA INFRAVENTURES · DURG
Units84
Booked29 of 84As of 2026-03-31
Construction progress51%As of 2026-03-31
Completion2030-03-21Revised · Proposed 2029-11-21
Registered on2024-12-02
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 6 quarters |
| Technical report | |
| Site & area | 3 site details · 84 unit types |
| Construction & progress | 4 progress details · 6 quarters |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 46 documents · 6 source links |
Registration
Registration
| Promoter | SABA INFRAVENTURES | |
|---|---|---|
| District | DURG | |
| Regulator | CG RERA | |
| Registration number | PCGRERA021224001855 | |
| Registered on | 2024-12-02 | |
| Project type | Residential Plotted Development | |
| Status (as filed) | New | |
| Proposed completion | 2029-11-21 | |
| Revised completion | 2030-03-21 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Diversion Order By Completent authority |
| Approval Letter of Town And Country Planning |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹94,12,000 | |
|---|---|---|
| Construction | ₹4,16,50,000 |
Quarterly money flows
| 2024-Q4 | ₹50,000 |
| 2025-Q1 | ₹48,57,143 |
| 2025-Q2 | ₹96,036 |
| 2025-Q3 | ₹22,32,919 |
| 2025-Q4 | ₹21,76,279 |
| 2026-Q1 | ₹8,97,492 |
Site & area
What does the land measure?
Site & area
Site & area
| Units | 84 | |
|---|---|---|
| Booked | 29 | |
| Booked as of | 2026-03-31 |
Unit types
| A-A-1 | 1 | 1 |
| A-A-2 | 1 | 1 |
| A-A-3 | 1 | 0 |
| A-A-4 | 1 | 1 |
| A-A-5 | 1 | 0 |
| A-A-6 | 1 | 0 |
| A-A-7 | 1 | 1 |
| A-A-8 | 1 | 1 |
| A-A-9 | 1 | 0 |
| A-A-10 | 1 | 0 |
| A-A-11 | 1 | 0 |
| A-A-12 | 1 | 0 |
| B-B-1 | 1 | 1 |
| B-B-2 | 1 | 1 |
| B-B-3 | 1 | 1 |
| B-B-4 | 1 | 0 |
| B-B-5 | 1 | 0 |
| B-B-6 | 1 | 0 |
| B-B-7 | 1 | 0 |
| B-B-8 | 1 | 0 |
| B-B-9 | 1 | 1 |
| B-B-10 | 1 | 1 |
| B-B-11 | 1 | 0 |
| B-B-12 | 1 | 1 |
| B-B-13 | 1 | 1 |
| B-B-14 | 1 | 1 |
| B-B-15 | 1 | 0 |
| B-B-16 | 1 | 0 |
| B-B-17 | 1 | 0 |
| C-C-1 | 1 | 1 |
| C-C-2 | 1 | 1 |
| C-C-3 | 1 | 1 |
| C-C-4 | 1 | 1 |
| C-C-5 | 1 | 0 |
| C-C-6 | 1 | 0 |
| C-C-7 | 1 | 0 |
| C-C-8 | 1 | 0 |
| C-C-9 | 1 | 0 |
| D-D-1 | 1 | 1 |
| D-D-2 | 1 | 0 |
| D-D-3 | 1 | 0 |
| D-D-4 | 1 | 0 |
| D-D-5 | 1 | 1 |
| D-D-6 | 1 | 0 |
| D-D-7 | 1 | 0 |
| D-D-8 | 1 | 0 |
| D-D-9 | 1 | 0 |
| E-E-1 | 1 | 1 |
| E-E-2 | 1 | 1 |
| E-E-3 | 1 | 1 |
| F-F-1 | 1 | 1 |
| F-F-2 | 1 | 0 |
| F-F-3 | 1 | 0 |
| F-F-4 | 1 | 0 |
| G-G-1 | 1 | 0 |
| G-G-2 | 1 | 0 |
| G-G-3 | 1 | 1 |
| G-G-4 | 1 | 0 |
| G-G-5 | 1 | 0 |
| G-G-6 | 1 | 0 |
| G-G-7 | 1 | 0 |
| G-G-8 | 1 | 0 |
| G-G-9 | 1 | 0 |
| G-G-10 | 1 | 0 |
| G-G-11 | 1 | 1 |
| G-G-12 | 1 | 0 |
| G-G-13 | 1 | 0 |
| G-G-14 | 1 | 1 |
| G-G-15 | 1 | 1 |
| G-G-16 | 1 | 1 |
| G-G-17 | 1 | 1 |
| X-X-1 | 1 | 0 |
| X-X-2 | 1 | 0 |
| X-X-3 | 1 | 0 |
| X-X-4 | 1 | 0 |
| X-X-5 | 1 | 0 |
| X-X-6 | 1 | 0 |
| X-X-7 | 1 | 0 |
| X-X-8 | 1 | 0 |
| X-X-9 | 1 | 0 |
| X-X-10 | 1 | 0 |
| X-X-11 | 1 | 0 |
| X-X-12 | 1 | 0 |
| X-X-13 | 1 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 51% | |
|---|---|---|
| As of | 2026-03-31 | |
| Proposed completion | 2029-11-21 | |
| Revised completion | 2030-03-21 |
Quarterly progress
| 2024-Q4 | 2% |
| 2025-Q1 | 9% |
| 2025-Q2 | 12% |
| 2025-Q3 | 44% |
| 2025-Q4 | 44% |
| 2026-Q1 | 51% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SABA INFRAVENTURES | |
|---|---|---|
| Type | Partnership | |
| Other projects in this city pack | 1 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_ongoing.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MjI4Mg==
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Diversion Order By Completent authority
- Demarcation of Land with Latitude and longitude of end points · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Document
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- Development Work Plan
- Development Cost Description · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- CA Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Brouchre · Sign in to download
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- CA Certificate
- Engg Certificate
- Architect Certificate
- Diversion Order By Completent authority
- Approval Letter of Town And Country Planning
- Development Permission from competent authorities