Overview
SEASONS AVENUE
ASIT MAVJIBHAI LAKUM · Bengaluru Urban
Units84
Booked18 of 84
Construction progress61%
Completion2024-03-30Revised · Proposed 2022-06-30
Registered on2018-01-20
Valid to2028-12-31
Approvals3
Complaints0
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Disputes & cases | 0 project complaints · 0 promoter complaints |
| Contract & costs | 3 cost heads · 4 quarters |
| Technical report | |
| Site & area | 6 site details · 57 unit types |
| Construction & progress | 4 progress details · 4 quarters · 7 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 76 documents · 11 source links |
Registration
Registration
| Promoter | ASIT MAVJIBHAI LAKUM | |
|---|---|---|
| District | Bengaluru Urban | |
| Regulator | K-RERA | |
| Registration number | PRM/KA/RERA/1251/309/PR/180120/001585 | |
| Registered on | 2018-01-20 | |
| Valid to | 2028-12-31 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | APPROVED | |
| Proposed completion | 2022-06-30 | |
| Revised completion | 2024-03-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Authority |
|---|---|
| Approved Plan | BIAPPA - Bangalore Airport Area Planning Authority |
| Commencement Certificate | |
| All NOCs from Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Complaints & cases
| Project complaints | 0 | |
|---|---|---|
| Promoter | 0 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,28,00,000 | |
|---|---|---|
| Construction | ₹11,62,00,000 | |
| Total | ₹14,90,00,000 |
Quarterly money flows
| 2025-26-Q3 | ₹17,15,700 |
| 2025-26-Q4 | ₹10,28,000 |
| 2026-27-Q1 | ₹1,10,58,669 |
| 2026-27-Q2 | ₹1,18,32,434 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 3,237 | |
|---|---|---|
| FAR | 1.999 | |
| Towers | 1 | |
| Maximum floors | 4 | |
| Units | 84 | |
| Booked | 18 |
Unit types
| 2BHK | 5 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 1BHK | 1 | Seasons Avenue | 1 |
| 1BHK | 1 | Seasons Avenue | 1 |
| 1BHK | 3 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 1BHK | 2 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 1 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 2BHK | 6 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 1BHK | 2 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 1BHK | 1 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 1BHK | 2 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 2 |
| 1BHK | 1 | Seasons Avenue | 2 |
| 1BHK | 1 | Seasons Avenue | 2 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 6 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 1BHK | 2 | Seasons Avenue | 3 |
| 1BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 1BHK | 1 | Seasons Avenue | 3 |
| 1BHK | 1 | Seasons Avenue | 3 |
| 1BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 3 |
| 1BHK | 1 | Seasons Avenue | 3 |
| 1BHK | 1 | Seasons Avenue | 3 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 2BHK | 5 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 1BHK | 3 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 1BHK | 1 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 1BHK | 2 | Seasons Avenue | 4 |
| 2BHK | 1 | Seasons Avenue | 4 |
| 1BHK | 1 | Seasons Avenue | 4 |
| 1BHK | 1 | Seasons Avenue | 4 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 61% | |
|---|---|---|
| Start | 2017-07-05 | |
| Proposed completion | 2022-06-30 | |
| Revised completion | 2024-03-30 |
Quarterly progress
| 2025-26-Q3 | 2026-01-06 | 37% | 12 |
| 2025-26-Q4 | 2026-04-13 | 60% | 12 |
| 2026-27-Q1 | 2026-07-15 | 61% | 16 |
| 2026-27-Q2 | 2026-10-14 | 61% | 18 |
Extensions
| 2023-03-30 | Covid Extension | |
| 2024-03-30 | Section 6 Extension | |
| 2028-12-31 | Further Extension | |
| 2023-03-30 | Covid Extension | |
| 2024-03-30 | Section 6 Extension | |
| 2028-12-31 | Further Extension | |
| 2023-09-22 | 2024-03-30 | Project extension |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ASIT MAVJIBHAI LAKUM | |
|---|---|---|
| Type | Individual | |
| Escrow bank | Axis Bank | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://mahitikanaja.karnataka.gov.in/Rera/api/Rera/ProjectViewDetails
- https://rera.karnataka.gov.in/projectDetails
- https://rera.karnataka.gov.in/projectViewDetails
- https://rera.karnataka.gov.in/viewAllProjectOrders
- https://rera.karnataka.gov.in/viewAllProjects?language=en
- https://rera.karnataka.gov.in/viewRenewalProjects
- Other · Sign in to download
- Architect Certificate for Work Completion Schedule till Date · Sign in to download
- Engineer Certificate for Work Completion Schedule till Date · Sign in to download
- CA Certificate for Funds Utilization · Sign in to download
- Architect Certificate for Pending Work Completion Schedule. · Sign in to download
- Engineer Certificate for Pending Work Completion Schedule. · Sign in to download
- CA Certificate for Funds required for Project Completion · Sign in to download
- Consent letter from 2/3rd of Allottees · Sign in to download
- Other · Sign in to download
- Document 1 · Sign in to download
- Document 2 · Sign in to download
- Document 3 · Sign in to download
- Document 4 · Sign in to download
- Document 5 · Sign in to download
- Document 6 · Sign in to download
- Document 7 · Sign in to download
- Document 8 · Sign in to download
- Document 9 · Sign in to download
- Document 10 · Sign in to download
- Document 11 · Sign in to download
- Other · Sign in to download
- Commencement Certificate
- Approved Building/Plotting Plan
- Approved Layout Plan
- Land documents and Location · Sign in to download
- Approved Section Of Building/Infrastructure Plan of Plotting
- Area Development Plan Of Project Area
- Performa of Allotment Letter · Sign in to download
- Brochure of Current Project · Sign in to download
- All NOCs from Authority
- Project Specification · Sign in to download
- Conversion Certificate under Sec 95 of the KLR Act 1961 · Sign in to download
- BWSSB · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Audited Profit and Loss Statement · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Cash Flow Statement · Sign in to download
- Cash Flow Statement · Sign in to download
- Auditor's Report · Sign in to download
- Auditor's Report · Sign in to download
- Auditor's Report · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Income Tax Return Acknowledgement · Sign in to download
- Declaration (Form B) · Sign in to download
- Prospectus/Brochure · Sign in to download
- Other · Sign in to download
- Other · Sign in to download
- Form-4 Certificate issued by Chartered Accountant · 2026-01-06
- Form-5 Certificate issued by Architect · 2026-01-06
- Form-6 Certificate issued by Structural Engineer · 2026-01-06
- QPR · 2026-01-06
- Form-4 Certificate issued by Chartered Accountant · 2026-04-13
- Form-5 Certificate issued by Architect · 2026-04-13
- Form-6 Certificate issued by Structural Engineer · 2026-04-13
- QPR · 2026-04-13
- Form-4 Certificate issued by Chartered Accountant · 2026-07-15
- Form-5 Certificate issued by Architect · 2026-07-15
- Form-6 Certificate issued by Structural Engineer · 2026-07-15
- QPR · 2026-07-15
- Form-4 Certificate issued by Chartered Accountant · 2026-10-14
- Form-5 Certificate issued by Architect · 2026-10-14
- Form-6 Certificate issued by Structural Engineer · 2026-10-14
- QPR · 2026-10-14
- Registration certificate
- Registration certificate
- Registration certificate
- Other · Sign in to download
- Registration Certificate
- Renewed Certificate
- Commencement Certificate
- All NOCs from Authority
- Extension order
- Extension order
- Extension order · Sign in to download