Overview
SEASONS
KEYSTONE WORLD PVT LTD · Gurugram
Units175
Completion2029-09-30Proposed
Registered on2024-05-03
Valid to2029-09-30
Approvals11
Sections
| Property title & search report | |
|---|---|
| Approvals | 11 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 6 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 41 documents · 3 source links |
Registration
Registration
| Promoter | KEYSTONE WORLD PVT LTD | |
|---|---|---|
| District | Gurugram | |
| Regulator | HRERA Gurugram | |
| Registration number | GGM/823/555/2024/50 DATED 03.05.2024 | |
| Registered on | 2024-05-03 | |
| Valid to | 2029-09-30 | |
| Status (as filed) | Registered | |
| Proposed completion | 2029-09-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | 67 of 2011 dated 16-07-2011 valid till 15-07-2026 | Town & Country Planning Department | |
| Layout Plan | |||
| Building Plan | 2024-02-13 | ||
| I. BUILDING PLAN | 2024-02-13 | ||
| II. AAI | 2023-09-01 | ||
| III. ELECTRICAL LOAD NOC | 2021-01-04 | ||
| IV. FOREST NOC | 2013-08-27 | ||
| V. WATER ASSURANCE | 2023-08-16 | ||
| VI. SEWERAGE ASSURANCE | 2023-08-18 | ||
| VII. STROM WATER ASSURANCE | 2024-02-16 | ||
| VIII. FIRE SCHEME APPROVAL | 2024-03-22 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹28,39,58,000 | |
|---|---|---|
| Construction | ₹1,30,09,99,000 | |
| Total | ₹2,45,79,79,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 16,329.07 | |
|---|---|---|
| FAR | 1.78 | |
| Units | 175 |
Unit types
| Apartment/Shops/Other Buildings | 106.37 | 25 |
| Apartment/Shops/Other Buildings | 106.16 | 25 |
| Apartment/Shops/Other Buildings | 106.38 | 25 |
| Apartment/Shops/Other Buildings | 106.15 | 25 |
| Apartment/Shops/Other Buildings | 105.78 | 25 |
| Apartment/Shops/Other Buildings | 139.13 | 50 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-04-01 | |
|---|---|---|
| Proposed completion | 2029-09-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | KEYSTONE WORLD PVT LTD | |
|---|---|---|
| Type | Company | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/2
- https://haryanarera.gov.in/view_project/project_preview_open/2826
- https://nominatim.openstreetmap.org/search?q=sector+77%2C+Gurugram%2C+Haryana%2C+India&format=jsonv2&addressdetails=1&namedetails=1&limit=10&countrycodes=in&accept-language=en&dedupe=1
- Registration Certificate · 2024-05-03
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2024-02-24
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2024-02-24 · Sign in to download
- PARKING PLAN · 2024-02-26
- DEMARCATION PLAN · 2024-02-26
- ZONING PLAN · 2024-02-26
- ELEVATION PLAN · 2024-02-26
- BRIII · 2024-02-26 · Sign in to download
- SECTION PLAN · 2024-02-26
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2024-02-26
- WATER ASSURANCE · 2024-02-26 · Sign in to download
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2024-05-03
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2024-05-03
- COMMUNITY BUILDING ROOF PLAN · 2024-06-07
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2024-06-07 · Sign in to download
- COPY OF ARCHITECTURAL AND PLUMBING - PLAN - SITE PLAN · 2024-06-07
- COPY OF ARCHITECTURAL AND PLUMBING - PLAN - BASEMENT 1 · 2024-06-07
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2024-06-07 · Sign in to download
- COMMUNITY BUILDING FLOOR PLAN · 2024-06-07
- COST INCURRED ON PROJECT CA · 2024-06-07 · Sign in to download
- FIRE APPROVAL - FIRE FIGHTING SCHEMATIC DIAGRAM LAYOUT · 2024-06-07
- FIRE APPROVAL -COMMUNITY BUILDING GROUND FLOOR FIRE & VENTILATION LAYOUT · 2024-06-07
- BANK UNDERTAKING · 2024-06-07 · Sign in to download
- SEWERAGE NOC · 2024-06-07
- LOI · 2024-06-07 · Sign in to download
- STORM WATER ASSURANCE · 2024-06-07 · Sign in to download
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2024-06-07
- ARAWALI CLEARANCE · 2024-06-07
- ELECTRICAL LOAD AVAILABILITY · 2024-06-07 · Sign in to download
- LC IV · 2024-06-07 · Sign in to download
- BIP - KEYSTONE · 2024-06-07 · Sign in to download
- NON ENCUMBRANCE CERTIFICATE · 2024-06-07 · Sign in to download
- CERTIFICATE FOR UNITS · 2024-06-07 · Sign in to download
- FIRE APPROVAL -ELETRICAL SITE PLAN WITH LIGHTING PROTECTION SYSTEM · 2024-06-07
- APPROVED FIRE QUESTIONNAIRE · 2024-06-07 · Sign in to download
- ASSURANCES - STP TREATED WATER, DRINKING WATER AND SEWAGE · 2024-06-07 · Sign in to download
- AIRPORT HEIGHT CLEARANCE NOC · 2024-06-07
- SITE OVERLAP WITH KHASARA (3)-MODEL · 2024-06-07 · Sign in to download
- FIRE SCHME APPROVAL · 2024-06-07
- FLOOR PLAN · 2024-06-07
- FOREST NOC · 2024-06-07