Overview
Sector 76, 77, 78, 79 and 80
Greater Mohali Area Development Authority (GMADA) · Sahibzada Ajit Singh Nagar (Mohali)
Units279
Completion2018-12-31Proposed
Valid to2018-12-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 17 unit types |
| Construction & progress | 2 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 11 documents · 4 source links |
Registration
Registration
| Promoter | Greater Mohali Area Development Authority (GMADA) | |
|---|---|---|
| District | Sahibzada Ajit Singh Nagar (Mohali) | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-SAS81-PR0389 | |
| Valid to | 2018-12-31 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | On-going | |
| Proposed completion | 2018-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹20,77,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,49,531.63 | |
|---|---|---|
| Units | 279 |
Unit types
| Plot 5 marla | 126.465 | 24 | SECTOR 77 |
| Plot 6 marla | 151.757 | 14 | SECTOR 77 |
| Plot 8 marla | 202.343 | 4 | SECTOR 77 |
| Plot 4 marla | 101.172 | 15 | SECTOR 77 |
| Plot 12 marla | 303.515 | 24 | SECTOR 77 |
| Plot 1 kanal | 505.857 | 1 | SECTOR 77 |
| Plot 10 marla | 252.929 | 9 | SECTOR 77 |
| Plot 2 kanal | 1,011.71 | 4 | SECTOR 78 |
| Plot 6 marla | 151.757 | 11 | SECTOR 79 |
| Plot 8 marla | 202.343 | 57 | SECTOR 79 |
| Plot 10 marla | 252.929 | 22 | SECTOR 79 |
| Plot 16 marla | 404.686 | 10 | SECTOR 79 |
| Plot 4 marla | 101.172 | 16 | SECTOR 80 |
| Plot 6 marla | 151.757 | 20 | SECTOR 80 |
| Plot 8 marla | 202.343 | 15 | SECTOR 80 |
| Plot 10 marla | 252.929 | 20 | SECTOR 80 |
| Plot 1 kanal | 505.857 | 13 | SECTOR 80 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-04-18 | |
|---|---|---|
| Proposed completion | 2018-12-31 |
Quarterly progress
| Quarter | Filed on |
|---|---|
| 2023-Q4 | 2024-01-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | Greater Mohali Area Development Authority (GMADA) | |
|---|---|---|
| Type | Authority | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 9 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=11014&inPromoter_ID=1273&inPromoterType=2
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Architects Certificate (Form 1)
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Engineers Certificate (Form 2)
- Commencement Certificate (Mega Project Category) · Sign in to download
- Other Document (20th meeting of authority) · 2016-04-18 · Sign in to download
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- 2023-Q4 · 2024-01-15