Overview
SFS LA FORTUNA
SKYLINE FOUNDATIONS AND STRUCTURES PRIVATE LIMITED · Pin Code 682021
Units31
Booked24 of 31
Construction progress45%
Completion2028-11-30Revised · Proposed 2029-03-30
Registered on2024-09-24
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Technical report | |
| Site & area | 5 site details · 5 unit types |
| Construction & progress | 4 progress details · 9 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details · 3 professional firms |
| The evidence | |
| Sources | 59 documents · 5 source links |
Registration
Registration
| Promoter | SKYLINE FOUNDATIONS AND STRUCTURES PRIVATE LIMITED | |
|---|---|---|
| District | Ernakulam | |
| Locality | Pin Code 682021 | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/ERN/189/2024 | |
| Registered on | 2024-09-24 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Inprogress | |
| Proposed completion | 2029-03-30 | |
| Revised completion | 2028-11-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | BP/6637/2024 | 2024-07-20 | 2029-07-19 | Thrikkakara Municipality |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,475 | |
|---|---|---|
| Built-up (m²) | 12,432.47 | |
| Towers | 0 | |
| Units | 31 | |
| Booked | 24 |
Unit types
| 4BHK | 14 | 13 | SFS LA FORTUNA |
| 4BHK | 2 | 0 | SFS LA FORTUNA |
| 4BHK | 13 | 10 | SFS LA FORTUNA |
| 4BHK | 1 | 0 | SFS LA FORTUNA |
| 4BHK | 1 | 1 | SFS LA FORTUNA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 45% | |
|---|---|---|
| Start | 2024-09-05 | |
| Proposed completion | 2029-03-30 | |
| Revised completion | 2028-11-30 |
Quarterly progress
| Quarter |
|---|
| 2026-2027 Q1 |
| 2026-2027 Q2 |
| 2025-2026 Q1 |
| 2025-2026 Q2 |
| 2025-2026 Q3 |
| 2025-2026 Q4 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
Extensions
| Valid to |
|---|
| 2028-11-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SKYLINE FOUNDATIONS AND STRUCTURES PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | State Bank of India | |
| Other projects in this city pack | 22 |
Professional firms
| Role | Firm |
|---|---|
| Architect | Mathai Mathew Architects |
| Engineer | Associated Structural Consultants |
| CA | PSDY & Associates |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/projects/11657
- https://rera.kerala.gov.in/projects?district=595&page=21
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=qK5cD0PHpOkLKoaeZ8C2XW83EN2FcazJFSqXNaWp5Wt7nIiF2we2SHWEFZSZaph%2FxcToFOK9y6jCLWVxmXCi8mH2O4jQp3qp20%2FtKbRocvE9sS62%2FCVkhwu6%2BJGjkVdh9Ts6ERcIF5Ri%2FaNWLfcexVTlXabTmzzYF0kMmvkIjuS1pxS%2FNDx1cg%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=11657&Division=1&UserID=30164&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Extension Certificate · Sign in to download
- Extension Order · Sign in to download
- Signed project certificate · 2024-09-24
- Extension certificate · 2025-06-04 · Sign in to download
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Sanctioned Plans (Provide a clear remark for each drawing such as ground floor ,1st floor, elevation ,section etc) · 2024-07-23
- Copy of Valid Building Permit · 2024-07-23
- Copy of Valid Development Permit (For villa projects & plot development projects) · 2024-07-23
- Detailed technical specifications to be adopted in the project · 2024-07-30 · Sign in to download
- Location details of the project with clear demarcation of land with boundaries including Latitude and Longitude of end points · 2024-07-25 · Sign in to download
- Site Plan / Site Map · 2024-07-23
- Other · 2024-07-23 · Sign in to download
- Other · 2024-07-23 · Sign in to download
- Other · 2024-07-23 · Sign in to download
- Other · 2024-07-23 · Sign in to download
- Other · 2024-07-23 · Sign in to download
- Clearance from Airport Authority of India · 2024-07-23 · Sign in to download
- Clearance from Coastal Zone Management Authority · 2024-07-23 · Sign in to download
- Clearance from National Highways / Railways / Other Relevant Departments · 2024-07-23 · Sign in to download
- Concurrence / Layout Approval of LSG planning department · 2024-08-21
- Consent to establish (Clearance from Pollution Control Board) · 2024-07-23 · Sign in to download
- Environment Clearance · 2024-07-23 · Sign in to download
- Initial NOC from Fire and Rescue department · 2024-07-23
- Permission from Water and sewerage department · 2024-07-23 · Sign in to download
- Charts and the project schedule · 2024-08-27 · Sign in to download
- Charts and the project schedule · 2025-11-10 · Sign in to download
- List and details of common amenities · 2024-07-30 · Sign in to download
- Plan for Drinking water service to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of firefighting to be executed in the proposed project · 2024-07-24
- Plan of Use of renewable energy to be executed in the proposed project · 2024-07-24