Overview
SHANOOR AAMBIENCE
SHANOOR PROJECTS AND REALTORS PVT LTD · Thrippoonithura
Units126
Booked77 of 126
Construction progress72%
Completion2029-07-30Revised · Proposed 2023-12-30
Registered on2021-09-01
Approvals1
Cases1
Complaints1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 1 case · 1 project complaint · 1 registration detail |
| Technical report | |
| Site & area | 5 site details · 7 unit types |
| Construction & progress | 4 progress details · 10 quarters · 1 extension |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 4 documents · 7 source links |
Registration
Registration
| Promoter | SHANOOR PROJECTS AND REALTORS PVT LTD | |
|---|---|---|
| District | Ernakulam | |
| Locality | Thrippoonithura | |
| Regulator | K-RERA Kerala | |
| Registration number | K-RERA/PRJ/342/2020 | |
| Registered on | 2021-09-01 | |
| Project type | Residential (Apartment) | |
| Status (as filed) | Registration Expired Project (official expired filter) | |
| Proposed completion | 2023-12-30 | |
| Revised completion | 2029-07-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Number | Date | Valid to | Authority |
|---|---|---|---|---|
| Building Permit | PW2/BA-348/15-16 | 2023-01-23 | 2027-01-16 | Tripunithura Municipality |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Cases
| Case number | Forum | Kind |
|---|---|---|
| 277/2022 | K-RERA Kerala | Complaint |
Complaints & cases
| Cases | 1 | |
|---|---|---|
| Project complaints | 1 |
Registration status
| Status | Registration Expired Project (official expired filter) |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 4,281.35 | |
|---|---|---|
| Built-up (m²) | 18,628 | |
| Towers | 0 | |
| Units | 126 | |
| Booked | 77 |
Unit types
| 2BHK | 18 | 18 | MPS Aambience Tower 2 |
| 3BHK | 18 | 18 | MPS Aambience Tower 2 |
| 3BHK | 18 | 18 | MPS Aambience Tower 2 |
| 3BHK | 18 | 18 | MPS Aambience Tower 2 |
| 2BHK | 18 | 1 | Aambience Tower 1 |
| 3BHK | 18 | 0 | Aambience Tower 1 |
| 3BHK | 18 | 4 | Aambience Tower 1 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 72% | |
|---|---|---|
| Start | 1900-01-01 | |
| Proposed completion | 2023-12-30 | |
| Revised completion | 2029-07-30 |
Quarterly progress
| Quarter |
|---|
| 2025-2026 Q1 |
| 2024-2025 Q1 |
| 2024-2025 Q2 |
| 2024-2025 Q3 |
| 2024-2025 Q4 |
| 2023-2024 Q1 |
| 2022-2023 Q2 |
| 2021-2022 Q1 |
| 2021-2022 Q2 |
| 2020-2021 Q4 |
Extensions
| Valid to |
|---|
| 2029-07-30 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHANOOR PROJECTS AND REALTORS PVT LTD | |
|---|---|---|
| Type | Company | |
| Escrow bank | State Bank Of India | |
| Other projects in this city pack | 13 |
Sources
Sources
Source URLs & documents
- https://rera.kerala.gov.in/complaint-list?ruling_by=all&page=53
- https://rera.kerala.gov.in/explore-projects?status=expired&page=7
- https://rera.kerala.gov.in/projects/116
- https://rera.kerala.gov.in/projects?district=595&page=21
- https://reraonline.kerala.gov.in/PrintPreview/PrintPreview?q=LyAMXQUYnPHbX%2FPYMZmLqO4BysO0mg%2FMXpLyFMeOuJITA790ry6oRJA1XW3RCyN9mxaWA65zxuuPfm8LJCA7FUs2SEYgCx9LN8HgiKq0CMLzUxdc5tMgvLGR7HtERaTcRV7ZikRxfgrcAdm4zp%2F4A30Jo2hxok6QNnuy74zRUQRH84sr9RQ6SA%3D%3D
- https://reraonline.kerala.gov.in/ProjectStatusPublic/ProjectStatusGeneralInfo?ProjectID=116&Division=1&UserID=30360&RoleID=1&PAction=_ProjectStatusGeneralInfo
- https://reraonline.kerala.gov.in/SearchList/Search
- Application · Sign in to download
- Certificate
- Signed project certificate · 2021-09-01
- Copy of Valid Building Permit · 2026-07-20