SHANTI SAROVAR

SHIVANK KEDIA · BALODABAZAR
Units57
Booked57 of 57As of 2024-06-30
Construction progress100%As of 2024-06-30
Completion2024-09-14Revised · Proposed 2020-12-31
Registered on2020-03-04

Sections

Property title & search report
Contract & costs2 cost heads · 18 quarters
Technical report
Site & area3 site details · 57 unit types
Construction & progress4 progress details · 18 quarters
Developer & finance
Developer4 developer details
The evidence
Sources89 documents · 3 source links

Registration

Registration

PromoterSHIVANK KEDIA
DistrictBALODABAZAR
RegulatorCG RERA
Registration numberPCGRERA040320001103
Registered on2020-03-04
Project typePlotted Development
Status (as filed)New
Proposed completion2020-12-31
Revised completion2024-09-14