Overview
SHANTI SNEH
SRI MATESHWARI CONSTRUCTIONS · Patna
Units40
Completion2019-06-23Proposed
Registered on2018-05-08
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 1 unit type |
| Construction & progress | 2 progress details · 14 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 31 documents · 19 source links |
Registration
Registration
| Promoter | SRI MATESHWARI CONSTRUCTIONS | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP00026-2/31/R-16/2018 | |
| Registered on | 2018-05-08 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | Completed | |
| Proposed completion | 2019-06-23 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹2,20,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 1,714.05 | |
|---|---|---|
| Built-up (m²) | 4,216.37 | |
| FAR | 2.46 | |
| Towers | 1 | |
| Units | 40 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 40 | Shanti Sneh |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2016-06-24 | |
|---|---|---|
| Proposed completion | 2019-06-23 |
Quarterly progress
| 2021-Q4 | 2022-02-08 |
| 2021-Q3 | 2022-02-08 |
| 2021-Q2 | 2022-02-08 |
| 2021-Q1 | 2022-02-08 |
| 2020-Q4 | 2022-02-08 |
| 2020-Q3 | 2022-02-08 |
| 2020-Q2 | 2020-10-23 |
| 2020-Q1 | 2020-07-02 |
| 2019-Q4 | 2020-01-22 |
| 2019-Q3 | 2019-10-25 |
| 2019-Q2 | 2019-07-24 |
| 2019-Q1 | 2019-04-30 |
| 2018-Q4 | 2019-01-31 |
| 2018-Q3 | 2018-12-28 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SRI MATESHWARI CONSTRUCTIONS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | Axis Bank | |
| Other projects in this city pack | 10 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP2511201700026-2
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP2511201700026-2
- https://rera.bihar.gov.in/RegisteredPP.aspx
- https://rera.bihar.gov.in/map.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Audited Profit Loss Statement · Sign in to download
- Balance Sheet · Sign in to download
- Document
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q3-Oct to Dec / 2021-2022 · 2022-02-08
- Q2-Jul to Sep / 2021-2022 · 2022-02-08
- Q1-Apr to Jun / 2021-2022 · 2022-02-08
- Q4-Jan to Mar / 2020-2021 · 2022-02-08
- Q3-Oct to Dec / 2020-2021 · 2022-02-08
- Q2-Jul to Sep / 2020-2021 · 2022-02-08
- Q1-Apr to Jun / 2020-2021 · 2020-10-23
- Q4-Jan to Mar / 2019-2020 · 2020-07-02
- Q3-Oct to Dec / 2019-2020 · 2020-01-22
- Q2-Jul to Sep / 2019-2020 · 2019-10-25
- Q1-Apr to Jun / 2019-2020 · 2019-07-24
- Q4-Jan to Mar / 2018-2019 · 2019-04-30
- Q3-Oct to Dec / 2018-2019 · 2019-01-31
- Q2-Jul to Sep / 2018-2019 · 2018-12-28
- Project Photogragh · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2021-Q4 · 2022-02-08
- 2021-Q2 · 2022-02-08
- 2021-Q1 · 2022-02-08
- 2020-Q4 · 2022-02-08
- 2020-Q3 · 2022-02-08
- 2020-Q2 · 2020-10-23
- 2020-Q1 · 2020-07-02
- 2019-Q4 · 2020-01-22
- 2019-Q3 · 2019-10-25
- 2019-Q2 · 2019-07-24
- 2019-Q1 · 2019-04-30
- 2018-Q4 · 2019-01-31
- 2018-Q3 · 2018-12-28