DOSLChhattisgarh Workspace

Overview

SHASVAT NAGAR

DHANESHWAR PANDEY & VIJAY PANDEY · BASTAR
Booked31As of 2021-06-30
Construction progress100%As of 2021-06-30
Completion2021-07-31Revised · Proposed 2020-01-31
Registered on2019-01-11
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area2 site details · 1 unit type
Construction & progress4 progress details · 10 quarters
Developer & finance
Developer4 developer details
The evidence
Sources76 documents · 6 source links

Registration

Registration

PromoterDHANESHWAR PANDEY & VIJAY PANDEY
DistrictBASTAR
RegulatorCG RERA
Registration numberPCGRERA110119000890
Registered on2019-01-11
Project typePlotted Development
Status (as filed)New
Proposed completion2020-01-31
Revised completion2021-07-31