Overview
SHITAL CHAYA
DIKSHA BUILDCON PRIVATE LIMITED · Patna
Units20
Completion2023-11-25Proposed
Registered on2021-11-25
Approvals2
Sections
| Property title & search report | |
|---|---|
| Approvals | 2 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 5 site details · 2 unit types |
| Construction & progress | 2 progress details · 8 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 19 documents · 14 source links |
Registration
Registration
| Promoter | DIKSHA BUILDCON PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP45613-1/109/R-1241/2021 | |
| Registered on | 2021-11-25 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2023-11-25 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.) |
| Notice of Commencement |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹3,60,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 2,207 | |
|---|---|---|
| Built-up (m²) | 1,785.44 | |
| FAR | 2.19 | |
| Towers | 1 | |
| Units | 20 |
Unit types
| Type | Units | Tower |
|---|---|---|
| 3 BHK | 8 | SHITAL CHAYA |
| 2 BHK | 12 | SHITAL CHAYA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2021-08-20 | |
|---|---|---|
| Proposed completion | 2023-11-25 |
Quarterly progress
| 2024-Q2 | 2024-07-14 |
| 2023-Q3 | 2024-07-25 |
| 2023-Q2 | 2024-07-25 |
| 2023-Q1 | 2023-04-14 |
| 2022-Q4 | 2023-04-14 |
| 2022-Q3 | 2023-04-14 |
| 2022-Q2 | 2022-09-14 |
| 2022-Q1 | 2022-09-14 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | DIKSHA BUILDCON PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP07182021145613-1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP07182021145613-1
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Approved Layout Plan
- Area Development Plan
- Brochure of Current Project · Sign in to download
- Declaration (Form B) · Sign in to download
- Land documents & Location · Sign in to download
- Notice of Commencement
- Sanctioned building Plan
- Sanctioned Layout Plan
- Q1-Apr to Jun / 2024-2025 · 2024-07-14
- Q2-Jul to Sep / 2023-2024 · 2024-07-25
- Q1-Apr to Jun / 2023-2024 · 2024-07-25
- Q4-Jan to Mar / 2022-2023 · 2023-04-14
- Q3-Oct to Dec / 2022-2023 · 2023-04-14
- Q2-Jul to Sep / 2022-2023 · 2023-04-14
- Q1-Apr to Jun / 2022-2023 · 2022-09-14
- Q4-Jan to Mar / 2021-2022 · 2022-09-14
- Any other Project Related Documents(enviromental clearance, NOCs, IT Return etc.)
- Notice of Commencement
- 2024-Q2 · 2024-07-14
- 2023-Q3 · 2024-07-25
- 2023-Q2 · 2024-07-25
- 2023-Q1 · 2023-04-14
- 2022-Q4 · 2023-04-14
- 2022-Q3 · 2023-04-14
- 2022-Q2 · 2022-09-14
- 2022-Q1 · 2022-09-14