SHIVA RESIDENCY PHASE- II
SHIVA HOMES · RAIPUR
Construction progress100%As of 2018-09-30
Completion2018-06-30Proposed
Registered on2018-06-07
Approvals3
Sections
| Property title & search report | |
|---|---|
| Approvals | 3 approvals |
| Contract & costs | 2 cost heads · 1 quarter |
| Technical report | |
| Site & area | 2 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 3 developer details |
| The evidence | |
| Sources | 21 documents · 6 source links |
Registration
Registration
| Promoter | SHIVA HOMES | |
|---|---|---|
| District | RAIPUR | |
| Regulator | CG RERA | |
| Registration number | PCGRERA070618000098 | |
| Registered on | 2018-06-07 | |
| Project type | Group Housing | |
| Status (as filed) | Ongoing | |
| Proposed completion | 2018-06-30 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval |
|---|
| Approval Letter of Town And Country Planning |
| Building Permission from local Authority |
| Development Permission from competent authorities |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹0 | |
|---|---|---|
| Construction | ₹0 |
Quarterly money flows
| Quarter | Escrow balance |
|---|---|
| 2018-Q3 | ₹0 |
Site & area
What does the land measure?
Site & area
Unit types
| Type | Carpet (m²) | Units | Booked |
|---|---|---|---|
| 2BHK | 65 | 24 | 24 |
| 3BHK | 110 | 47 | 47 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 100% | |
|---|---|---|
| As of | 2018-09-30 | |
| Proposed completion | 2018-06-30 |
Quarterly progress
| Quarter | Progress |
|---|---|
| 2018-Q3 | 100% |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SHIVA HOMES | |
|---|---|---|
| Type | Other | |
| Other projects in this city pack | 6 |
Sources
Sources
Source URLs & documents
- https://rera.cgstate.gov.in/Approved_project_List.aspx
- https://rera.cgstate.gov.in/Approved_project_List_completed.aspx
- https://rera.cgstate.gov.in/Promoter_Reg_Only_View_Application_new.aspx?MyID=MTgz
- Registration Certificate · Sign in to download
- Fee Calculation Sheet · Sign in to download
- Colonizer Registration Certiticate · Sign in to download
- Approval Letter of Town And Country Planning
- Sanctioned Layout Plan
- Building Permission from local Authority
- Development Permission from competent authorities
- Project Specifications · Sign in to download
- Brief Details of Current Project along with Stilt and Cover Parking Details (ANNEX-11) · Sign in to download
- Common Area Facilities · Sign in to download
- Development Team Details · Sign in to download
- CA Certificate(For New Project (ANNEXURE-01) and FOR Ongoing Project (ANNEXURE-02))
- Undertaking by the Promoter for pending documents (ANNEX-08) · Sign in to download
- Engineer Certificate
- Self Declaration by the Promoter for those documents which are not applicable (ANNEX-07) · Sign in to download
- CA Certificate
- Architect Certificate
- Audit Report
- Completion Certificate by Architect · Sign in to download
- Completion Certificate by Competent Authority · Sign in to download
- Brouchre · Sign in to download
- Approval Letter of Town And Country Planning
- Building Permission from local Authority
- Development Permission from competent authorities