SHOBHA BADAVANE PHASE 2

MOHAMMED ZIYAULLA · Shivamogga
Completion2021-12-29Proposed
Registered on2022-06-17
Approvals8
Complaints0

Sections

Property title & search report
Approvals8 approvals
Disputes & cases0 project complaints · 0 promoter complaints
Contract & costs3 cost heads
Technical report
Construction & progress2 progress details
Developer & finance
Developer4 developer details
The evidence
Sources95 documents · 11 source links

Registration

Registration

PromoterMOHAMMED ZIYAULLA
DistrictShivamogga
RegulatorK-RERA
Registration numberPRM/KA/RERA/1271/486/PR/170622/005005
Registered on2022-06-17
Project typePlotted Development
Status (as filed)APPROVED