SHREE AASHRYA
JANAK NANDINI INFRASTRUCTURES PRIVATE LIMITED · GONER
Units416
Booked271 of 416As of 2025-09-30
Completion2023-03-31Revised · Proposed 2017-04-16
Registered on2017-09-04
Valid to2026-07-31
Approvals1
Sections
| Property title & search report | |
|---|---|
| Approvals | 1 approval |
| Disputes & cases | 2 registration details |
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 7 site details · 6 unit types |
| Construction & progress | 3 progress details · 1 quarter · 4 extensions |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 33 documents · 10 source links |
Registration
Registration
| Promoter | JANAK NANDINI INFRASTRUCTURES PRIVATE LIMITED | |
|---|---|---|
| District | Jaipur | |
| Locality | GONER | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2017/135 | |
| Registered on | 2017-09-04 | |
| Valid to | 2026-07-31 | |
| Project type | Group Housing | |
| Status (as filed) | LAPSED | |
| Proposed completion | 2017-04-16 | |
| Revised completion | 2023-03-31 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Approval | Date | Authority |
|---|---|---|
| Revised Building Plan | 2017-07-28 | Jaipur Development Authority |
Disputes & cases
Are there court cases or buyer complaints on this project?
Disputes & cases
Registration status
| Status | LAPSED | |
|---|---|---|
| Valid to | 2026-07-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹4,30,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹40,30,00,000 |
Quarterly money flows
| Quarter | Received | Escrow balance |
|---|---|---|
| 2025-Q3 | ₹0 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 9,675.03 | |
|---|---|---|
| Built-up (m²) | 18,198.77 | |
| Towers | 416 | |
| Maximum floors | 5 | |
| Units | 416 | |
| Booked | 271 | |
| Booked as of | 2025-09-30 |
Unit types
| EWS 1BHK (Block B) | 23.68 | 24 | 0 | SHREE AASHRYA |
| EWS 1BHK (Block B) | 21.96 | 129 | 77 | SHREE AASHRYA |
| LIG 2 BHK (Block G) | 39.26 | 130 | 126 | SHREE AASHRYA |
| LIG 2 BHK (BLOCK H) | 39.26 | 125 | 68 | SHREE AASHRYA |
| shop (Block H) | 30.11 | 4 | 0 | SHREE AASHRYA |
| shop (Block H) | 10.45 | 4 | 0 | SHREE AASHRYA |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2017-04-16 | |
|---|---|---|
| Proposed completion | 2017-04-16 | |
| Revised completion | 2023-03-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2025-Q3 | 2025-11-29 | 271 |
Extensions
| Valid to |
|---|
| 2023-03-31 |
| 2026-03-31 |
| 2024-03-31 |
| 2026-07-31 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | JANAK NANDINI INFRASTRUCTURES PRIVATE LIMITED | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | STATE BANK OF INDIA | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=OzFTsNFV5znG7_-P81ubhw
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/OzFTsNFV5znG7_-P81ubhw
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=OzFTsNFV5znG7%2F%2BP81ubhw%3D%3D&QuarterIdEnc=s291bsdE%2FxcYMFPaLLqdrQ%3D%3D&PT=1&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=yPSnimK%2BMjs%3D&type=U
- Registration Certificate
- OrderDoc · Sign in to download
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Copy Of Approved Site Plan
- NOC for environment
- NOC from Airport Authority of India
- Project Related Approval Documents (Other than Plotted)
- FormFUploadedPathString · Sign in to download
- FormFUploadedPathString · Sign in to download
- FormFUploadedPathString · Sign in to download
- PROJECTCERTIFICATE
- APPROVALDOCREVISEDBUILPLAN · 2017-07-28
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Url · Sign in to download
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Fire Fighting Provision
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download
- R1_UploadDoc · 2025-11-28 · Sign in to download
- R2_UploadDoc · 2025-11-28 · Sign in to download
- R3_UploadedPath · 2025-11-29 · Sign in to download
- RERAretentionAccount_UploadedPath · Sign in to download
- Revised Building Plan · 2017-07-28
- Extension order · Sign in to download
- Extension order · Sign in to download
- Extension order · Sign in to download