Overview
Shree Ganesh Astha Enclave
ORB DEVELOPER PRIVATE LIMITED · Patna
Units17
Booked5 of 17As of 2026-06-30
Construction progress33%As of 2026-06-30
Completion2029-05-21Proposed
Registered on2024-08-23
Valid to2029-05-21
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 7 site details · 5 unit types |
| Construction & progress | 4 progress details · 7 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 20 documents · 12 source links |
Registration
Registration
| Promoter | ORB DEVELOPER PRIVATE LIMITED | |
|---|---|---|
| District | Patna | |
| Regulator | RERA Bihar | |
| Registration number | BRERAP15647-4/142/R-1757/2024 | |
| Registered on | 2024-08-23 | |
| Valid to | 2029-05-21 | |
| Project type | Residential/Group Housing | |
| Status (as filed) | New Project Launch | |
| Proposed completion | 2029-05-21 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Sanctioned Building Plan (MAP) | 2023-04-11 | PATNA MUNICIPAL CORPORATION | |
| Notice of Commencement in form X | |||
| Environment Clearance | 2025-01-01 | ||
| Fire NOC | 2025-01-01 | ||
| Airport NOC | 2025-01-01 | ||
| Water Supply Permission | 2025-01-01 | ||
| Other approval | 2025-01-01 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹50,00,00,00,00,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 715.61 | |
|---|---|---|
| Built-up (m²) | 1,120.93 | |
| FAR | 1.65 | |
| Towers | 1 | |
| Units | 17 | |
| Booked | 5 | |
| Booked as of | 2026-06-30 |
Unit types
| 1 BHK | 1 | Shree Ganesh Astha Enclave |
| 1 BHK | 1 | Shree Ganesh Astha Enclave |
| 3 BHK | 6 | Shree Ganesh Astha Enclave |
| 2 BHK | 6 | Shree Ganesh Astha Enclave |
| 2 BHK | 3 | Shree Ganesh Astha Enclave |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Progress | 33% | |
|---|---|---|
| As of | 2026-06-30 | |
| Start | 2024-05-21 | |
| Proposed completion | 2029-05-21 |
Quarterly progress
| 2026-Q2 | 2026-07-29 | 33% | 5 |
| 2026-Q1 | 2026-05-01 | ||
| 2025-Q4 | 2026-01-31 | ||
| 2025-Q3 | 2025-11-01 | ||
| 2025-Q2 | 2025-08-11 | ||
| 2024-Q4 | 2025-01-15 | ||
| 2024-Q3 | 2025-01-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | ORB DEVELOPER PRIVATE LIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | CENTRAL BANK OF INDIA | |
| Other projects in this city pack | 3 |
Sources
Sources
Source URLs & documents
- https://rera.bihar.gov.in/Filanprint.aspx?id=RERAP06142019215647-4
- https://rera.bihar.gov.in/QPR/QPR-Show.aspx?pr=RERAP06142019215647&ld=pan&pj=RERAP06142019215647-4&f=2026-2027&q=1
- https://rera.bihar.gov.in/QRCODE.aspx?id=RERAP06142019215647-4
- https://rera.bihar.gov.in/RERASearchPdistrictwise.aspx
- https://rera.bihar.gov.in/RegisteredPP.aspx
- View
- Scan copy of Bank Pass Book/ Statement · Sign in to download
- Declaration (Form B) · Sign in to download
- Notice of Commencement in form X
- Permit Letter of MAP.
- Sanctioned building plan
- Sanctioned Layout Plan
- Q1 (Apr - Jun) / 2026-2027 · 2026-07-29
- Quarterly Progress Image · 2025-08-11
- Q4 (Jan - Mar) / 2025-2026 · 2026-05-01
- Q3 (Oct - Dec) / 2025-2026 · 2026-01-31
- Q2 (Jul - Sep) / 2025-2026 · 2025-11-01
- Q1 (Apr - Jun) / 2025-2026 · 2025-08-11
- Q3-Oct to Dec / 2024-2025 · 2025-01-15
- Q2-Jun to Sep / 2024-2025 · 2025-01-15
- Project Photogragh · Sign in to download
- Project Photogragh · Sign in to download
- Chartered Accountant Certificate (.pdf)
- Architect Certificate (.pdf)
- Engineer Certificate (.pdf)
- Notice of Commencement in form X
- 2026-Q1 · 2026-05-01
- 2025-Q4 · 2026-01-31
- 2025-Q3 · 2025-11-01
- 2025-Q2 · 2025-08-11
- 2024-Q4 · 2025-01-15
- 2024-Q3 · 2025-01-15