Overview
SHREE GOVINDAM
YATI BUILDESTATE LLP · Kunda road, Sirsi
Units0
Booked0 of 0As of 2020-09-30
Completion2021-12-31Revised · Proposed 2018-08-09
Registered on2018-11-05
Valid to2021-12-31
Sections
| Property title & search report | |
|---|---|
| Contract & costs | 3 cost heads · 1 quarter |
| Technical report | |
| Site & area | 6 site details · 46 unit types |
| Construction & progress | 3 progress details · 1 quarter |
| Developer & finance | |
| Developer | 4 developer details · 1 professional firm |
| The evidence | |
| Sources | 61 documents · 6 source links |
Registration
Registration
| Promoter | YATI BUILDESTATE LLP | |
|---|---|---|
| District | Jaipur | |
| Locality | Kunda road, Sirsi | |
| Regulator | Rajasthan RERA | |
| Registration number | RAJ/P/2018/843 | |
| Registered on | 2018-11-05 | |
| Valid to | 2021-12-31 | |
| Project type | Plotted | |
| Status (as filed) | COMPLETED | |
| Proposed completion | 2018-08-09 | |
| Revised completion | 2021-12-31 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹14,90,00,000 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹16,90,00,000 |
Quarterly money flows
| Quarter | Escrow balance |
|---|---|
| 2020-Q3 | ₹0 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 29,083.5 | |
|---|---|---|
| Built-up (m²) | 14,757.01 | |
| Towers | 163 | |
| Units | 0 | |
| Booked | 0 | |
| Booked as of | 2020-09-30 |
Unit types
| RESIDENTIAL PLOT 1,3,6,7,9,10,12-15,23-46,48-59,62-70,73-81,84-95,98-104,107-111,114,115,117,118,120 | 0 | 0 |
| RESIDENTIAL PLOT 2,8,11,71,72,97,112,116,119 | 0 | 0 |
| RESIDENTIAL PLOT 4 | 0 | 0 |
| RESIDENTIAL PLOT 5 | 0 | 0 |
| RESIDENTIAL PLOT 16 | 0 | 0 |
| RESIDENTIAL PLOT 17 | 0 | 0 |
| RESIDENTIAL PLOT 18 | 0 | 0 |
| RESIDENTIAL PLOT 19 | 0 | 0 |
| RESIDENTIAL PLOT 20 | 0 | 0 |
| RESIDENTIAL PLOT 21 | 0 | 0 |
| RESIDENTIAL PLOT 22 | 0 | 0 |
| RESIDENTIAL PLOT 47,60,83,96 | 0 | 0 |
| RESIDENTIAL PLOT 61, 82 | 0 | 0 |
| RESIDENTIAL PLOT 105 | 0 | 0 |
| RESIDENTIAL PLOT 106 | 0 | 0 |
| RESIDENTIAL PLOT 113 | 0 | 0 |
| RESIDENTIAL PLOT 121 | 0 | 0 |
| RESIDENTIAL PLOT 122 | 0 | 0 |
| RESIDENTIAL PLOT 123 | 0 | 0 |
| RESIDENTIAL PLOT 124 | 0 | 0 |
| RESIDENTIAL PLOT 125 | 0 | 0 |
| EWS E1 | 0 | 0 |
| EWS E2 | 0 | 0 |
| EWS E3 | 0 | 0 |
| EWS E4 | 0 | 0 |
| EWS E5 | 0 | 0 |
| EWS E6 | 0 | 0 |
| EWS E7 | 0 | 0 |
| EWS E8 | 0 | 0 |
| EWS E9 | 0 | 0 |
| EWS E10 | 0 | 0 |
| EWS E11 | 0 | 0 |
| EWS E12 | 0 | 0 |
| LIG L1 | 0 | 0 |
| LIG L2 | 0 | 0 |
| LIG L3 | 0 | 0 |
| LIG L4 | 0 | 0 |
| LIG L5 | 0 | 0 |
| LIG L6 | 0 | 0 |
| LIG L7 | 0 | 0 |
| LIG L8 | 0 | 0 |
| LIG L9 | 0 | 0 |
| LIG L10 | 0 | 0 |
| LIG L11 | 0 | 0 |
| LIG L12 | 0 | 0 |
| SHOP 1-14 | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2018-08-09 | |
|---|---|---|
| Proposed completion | 2018-08-09 | |
| Revised completion | 2021-12-31 |
Quarterly progress
| Quarter | Filed on | Booked |
|---|---|---|
| 2020-Q3 | 2022-06-16 | 0 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | YATI BUILDESTATE LLP | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | RAJASTHAN MARUDHARA GRAMIN BANK | |
| Other projects in this city pack | 1 |
Professional firms
| Role | Firm |
|---|---|
| Architect | CAD MAX CONSULTANCY PVT LTD |
Sources
Sources
Source URLs & documents
- https://rera.rajasthan.gov.in/ProjectDetail?id=q3FGebseKYihryoUx2TqVw
- https://reraapi.rajasthan.gov.in/api/web/Home/GetProjects
- https://reraapi.rajasthan.gov.in/api/web/Home/GetprojectDetailsbyDepecryValue
- https://reraapp.rajasthan.gov.in/HomeWebsite/ProjectDtlsWebsite/q3FGebseKYihryoUx2TqVw
- https://reraapp.rajasthan.gov.in/HomeWebsite/QPRSummaryWebSite?projectIdEnc=q3FGebseKYihryoUx2TqVw%3D%3D&QuarterIdEnc=Bt8V7wp2shPkjg4upO7p5A%3D%3D&PT=4&isUnderProcess=&QPRPId=0
- https://reraapp.rajasthan.gov.in/HomeWebsite/ViewProjectWebsite?id=mzGahUSODhI%3D&type=U
- Registration Certificate
- Advocate Search Report along with Search Fee Receipt · Sign in to download
- Declaration in FORM B(As per RAJ-RERA Rules) · Sign in to download
- Location with Demarcation (Upload KMZ/KML File) · Sign in to download
- Copy Of Approved Site Plan
- Other Approvals as may be required and obtained for the project (if any)
- Project Related Approval Documents (Plotted)
- Water Supply
- Rain Water Harvesting/ Recharging
- Sanitation(Storm Water Drainage, Sewerage, STP, Solid Water Disposal etc)
- Electrification(Transformer, Solar Energy etc)
- Others
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- SitePlanPath · 2018-08-27
- Site_Plan_Doc_Sanctioned
- RCertificate
- Memorandum · Sign in to download
- ArticleAssociation · Sign in to download