Overview
SHREE KRISHNA ENCLAVE
SIGNATURE INFRATECH PRIVATELIMITED · Jhajjar
Units150
Completion2027-02-28Proposed
Valid to2027-02-28
Approvals7
Sections
| Property title & search report | |
|---|---|
| Approvals | 7 approvals |
| Contract & costs | 3 cost heads |
| Technical report | |
| Site & area | 3 site details · 28 unit types |
| Construction & progress | 2 progress details |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 16 documents · 2 source links |
Registration
Registration
| Promoter | SIGNATURE INFRATECH PRIVATELIMITED | |
|---|---|---|
| District | Jhajjar | |
| Regulator | HRERA Panchkula | |
| Registration number | HRERA-PKL-JJR-368-2022 | |
| Valid to | 2027-02-28 | |
| Status (as filed) | Registered | |
| Proposed completion | 2027-02-28 |
Approvals
Is it approved for its use?
Approvals
Approvals
| Licence | license no 86 of2022 dated 06-07-2022 | Town & Country Planning Department | |
| Layout Plan | 2022-07-06 | ||
| Building Plan | |||
| I. LICENSE NO 86 OF 2022 DATED 06-07-2022 | 2022-07-06 | ||
| II. DRINKING WATER CONNECTION | 2022-08-16 | ||
| III. ELECTRICITY CONNECTION | 2022-08-16 | ||
| IV. SEWRAGE WATER CONNECTIO | 2022-08-16 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Land | ₹26,59,19,999.99999997 | |
|---|---|---|
| Construction | ₹0 | |
| Total | ₹38,67,66,000 |
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 32,071.284 | |
|---|---|---|
| FAR | 1 | |
| Units | 150 |
Unit types
| Plot | 20 | |
| Plot | 55 | |
| Plot | 5 | |
| Plot | 22 | |
| Plot | 2 | |
| Plot | 24 | |
| Plot | 2 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Plot | 1 | |
| Apartment/Shops/Other Buildings | 0 | 0 |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2022-10-01 | |
|---|---|---|
| Proposed completion | 2027-02-28 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | SIGNATURE INFRATECH PRIVATELIMITED | |
|---|---|---|
| Type | Company | |
| Escrow bank | HDFC BANK | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://haryanarera.gov.in/admincontrol/registered_projects/1
- https://haryanarera.gov.in/view_project/project_preview_open/2070
- Registration Certificate
- NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT · 2022-08-10 · Sign in to download
- CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT · 2022-08-10 · Sign in to download
- IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN · 2022-08-10
- IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN · 2022-08-10
- ZONING PLAN · 2022-08-10
- COPY OF LICENSE ALONG WITH SCHEDULE OF LAND · 2022-08-10
- SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN · 2022-08-23
- DEMARCATION PLAN · 2022-08-23
- A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS · 2022-08-23
- CASH FLOW STATEMENT OF THE PROPOSED PROJECT · 2022-08-23 · Sign in to download
- DEMARCATION PLAN · 2025-12-18
- ZOINING PLAN · 2025-12-18
- SERVICE PLAN · 2025-12-18
- STANDARD DESIGN · 2025-12-18 · Sign in to download
- Completion Certificate · 2026-06-01 · Sign in to download