Overview
SHREE MANOHAR ESTATE
PREMIER DEVELOPERS · Bathinda
Units366
Completion2029-05-02Proposed
Valid to2029-05-02
Approvals22
Sections
| Property title & search report | |
|---|---|
| Approvals | 22 approvals · 1 occupancy certificate |
| Contract & costs | 1 cost head |
| Technical report | |
| Site & area | 2 site details · 88 unit types |
| Construction & progress | 2 progress details · 6 quarters |
| Developer & finance | |
| Developer | 4 developer details |
| The evidence | |
| Sources | 54 documents · 31 source links |
Registration
Registration
| Promoter | PREMIER DEVELOPERS | |
|---|---|---|
| District | Bathinda | |
| Regulator | Punjab RERA | |
| Registration number | PBRERA-BTI08-PR1121 | |
| Valid to | 2029-05-02 | |
| Project type | (1) Commercial (Plotted Development) (2) Residential (Plotted Development) | |
| Status (as filed) | New Project | |
| Proposed completion | 2029-05-02 |
Approvals
Is it approved for its use?
Approvals
Approvals
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2024-11-29 |
| AAI Height NOC from Civil Aviation Department/ Airport Authority | Clearances (Received) | 2025-02-26 |
| CLU Certificate | ||
| CLU Certificate | ||
| Electric Substation NOC | 2025-06-19 | |
| Environment Clearance certificate/ NOC | Clearances (Received) | 2025-02-26 |
| License as Promoter from competent Authority | 2023-09-22 | |
| License to develop colony or society from Competent Authority | ||
| License to develop colony or society from Competent Authority | ||
| NOC from Fire Department/ Chief Fire Officer | 2024-12-12 | |
| NOC from Mining Department | 2024-08-29 | |
| NOC from NHAI/ PWD | 2024-12-17 | |
| Occupancy Certificate from Municipal/ Competent Authority | 2024-02-06 | |
| Other Document (Forest NOC) | 2025-02-10 | |
| Other Document (Forest NOC) | 2024-11-18 | |
| Other Document (Railway Noc) | Clearances (Received) | 2024-09-02 |
| Other Document (Road Access NOC) | 2025-02-13 | |
| Other Document (Solid Waste NOC) | 2024-08-08 | |
| Pollution Clearance from Punjab Pollution Control Board | 2025-09-09 | |
| Pollution Clearance from Punjab Pollution Control Board | 2024-09-16 | |
| Consent details of actual owner of Land | ||
| Consent details of actual owner of Land |
Occupancy certificate
| Status | Received | |
|---|---|---|
| Date | 2024-02-06 |
Contract & costs
What does a buyer commit to?
Contract & costs
Project costs
| Total | ₹9,17,01,000 |
|---|
Site & area
What does the land measure?
Site & area
Site & area
| Land area (m²) | 67,604.75 | |
|---|---|---|
| Units | 366 |
Unit types
| plot commercial 1-38 | 1,959.303 | 38 | COMMERCIAL PLOTS |
| Ress Plot No 35 44 71 | 346.158 | 3 | RESS PLOTS |
| PLOTs 138 152 | 246.748 | 2 | RESS PLOTS |
| PLOTs 161 166 174 179 | 492.384 | 4 | RESS PLOTS |
| PLOTs 154-160 167-173 | 1,688.874 | 14 | RESS PLOTS |
| PLOTs 162-165 | 484.997 | 4 | RESS PLOTS |
| PLOTs 175-178 | 485.388 | 4 | RESS PLOTS |
| PLOTs 180-207 | 3,511.735 | 28 | RESS PLOTS |
| PLOTs 316-317 | 122.26 | 2 | RESS PLOTS |
| PLOTs 57 | 110.977 | 1 | RESS PLOTS |
| PLOTs 139-151 | 1,584.545 | 13 | RESS PLOTS |
| PLOT No 253 | 124.216 | 1 | RESS PLOTS |
| plot 254 | 123.871 | 1 | RESS PLOTS |
| plot 255 | 120.72 | 1 | RESS PLOTS |
| plot 256 | 117.656 | 1 | RESS PLOTS |
| plot 257 | 114.777 | 1 | RESS PLOTS |
| plot 258 | 111.964 | 1 | RESS PLOTS |
| plot 259 | 120.873 | 1 | RESS PLOTS |
| plot 264 | 109.789 | 1 | RESS PLOTS |
| plot 265 | 107.372 | 1 | RESS PLOTS |
| plot 266 | 105.028 | 1 | RESS PLOTS |
| plot 267 | 102.698 | 1 | RESS PLOTS |
| plot 268 | 100.255 | 1 | RESS PLOTS |
| plot 269 | 97.315 | 1 | RESS PLOTS |
| plot 270 | 114.935 | 1 | RESS PLOTS |
| plot 271 | 112.908 | 1 | RESS PLOTS |
| plot 272 | 1,223.434 | 1 | RESS PLOTS |
| plot 273 | 121.399 | 1 | RESS PLOTS |
| plot 274 | 119.391 | 1 | RESS PLOTS |
| plot 275 | 117.201 | 1 | RESS PLOTS |
| plot 276 | 114.878 | 1 | RESS PLOTS |
| plot 277 | 112.614 | 1 | RESS PLOTS |
| plot 278 | 110.617 | 1 | RESS PLOTS |
| plot 279 | 108.732 | 1 | RESS PLOTS |
| plot 280 | 104.485 | 1 | RESS PLOTS |
| plot 281 | 90.505 | 1 | RESS PLOTS |
| plot 282 | 100.712 | 1 | RESS PLOTS |
| plot 283 | 103.478 | 1 | RESS PLOTS |
| plot 284 | 106.178 | 1 | RESS PLOTS |
| plot 285 | 108.739 | 1 | RESS PLOTS |
| plot 286 | 119.83 | 1 | RESS PLOTS |
| plot 287 | 122.699 | 1 | RESS PLOTS |
| plot 289 | 108.847 | 1 | RESS PLOTS |
| plot 290 | 110.811 | 1 | RESS PLOTS |
| plot 291 | 112.771 | 1 | RESS PLOTS |
| plot 292 | 114.72 | 1 | RESS PLOTS |
| plot 293 | 116.669 | 1 | RESS PLOTS |
| plot 294 | 118.599 | 1 | RESS PLOTS |
| plot 295 | 120.507 | 1 | RESS PLOTS |
| plot 296 | 122.414 | 1 | RESS PLOTS |
| plot 297 | 124.318 | 1 | RESS PLOTS |
| plot 298 | 121.498 | 1 | RESS PLOTS |
| plot 299 | 117.701 | 1 | RESS PLOTS |
| plot 300 | 113.925 | 1 | RESS PLOTS |
| plot 301 | 109.496 | 1 | RESS PLOTS |
| plot 302 | 105.403 | 1 | RESS PLOTS |
| plot 303 | 101.649 | 1 | RESS PLOTS |
| plot 304 | 107.207 | 1 | RESS PLOTS |
| plot 305 | 101.787 | 1 | RESS PLOTS |
| plot 306 | 93.967 | 1 | RESS PLOTS |
| plot 307 | 86.897 | 1 | RESS PLOTS |
| plot 308 | 100.151 | 1 | RESS PLOTS |
| plot 309 | 123.184 | 1 | RESS PLOTS |
| plot 314 | 113.881 | 1 | RESS PLOTS |
| plot 315 | 112.658 | 1 | RESS PLOTS |
| plot 318 | 123.475 | 1 | RESS PLOTS |
| plot 319 | 123.843 | 1 | RESS PLOTS |
| plot 320 | 120.995 | 1 | RESS PLOTS |
| plot 321 | 116.652 | 1 | RESS PLOTS |
| plot 322 | 112.258 | 1 | RESS PLOTS |
| plot 323 | 107.804 | 1 | RESS PLOTS |
| plot 324 | 103.277 | 1 | RESS PLOTS |
| plot 325 | 98.744 | 1 | RESS PLOTS |
| plot 326 | 94.188 | 1 | RESS PLOTS |
| plot 327 | 88.682 | 1 | RESS PLOTS |
| plot 328 | 85.337 | 1 | RESS PLOTS |
| Ress Plots No 1-34 | 4,258.853 | 34 | RESS PLOTS |
| Ress Plot NO. 137,153 | 249.684 | 2 | RESS PLOTS |
| Ress Plot No. 80 | 115.368 | 1 | RESS PLOTS |
| Ress Plot No. 226 | 125.4 | 1 | RESS PLOTS |
| Ress Plot 36-43 45-52 53-56 58-[redacted] 81-136 288 310-313 | 12,792.326 | 102 | RESS PLOTS |
| Ress Plot 208-225 | 1,505.029 | 18 | EWS PLOTS |
| Ress Plot 227-241 | 1,254.191 | 15 | EWS PLOTS |
| Ress Plots 242-252 | 919.74 | 11 | EWS PLOTS |
| plot 260 | 82.485 | 1 | EWS PLOTS |
| plot 261 | 82.795 | 1 | EWS PLOTS |
| plot 262 | 80.931 | 1 | EWS PLOTS |
| plot 263 | 81.288 | 1 | EWS PLOTS |
Construction & progress
How is it being built, and when will it be ready?
Construction & progress
Progress
| Start | 2024-05-03 | |
|---|---|---|
| Proposed completion | 2029-05-02 |
Quarterly progress
| 2025-Q2 | 2025-07-15 |
| 2025-Q3 | 2026-01-25 |
| 2025-Q4 | 2026-01-25 |
| 2026-Q1 | 2026-04-14 |
| 2026-Q2 | 2026-07-12 |
| 2026-Q3 | 2026-10-15 |
Developer
Can the developer deliver?
Developer
Promoter
| Promoter | PREMIER DEVELOPERS | |
|---|---|---|
| Type | Partnership | |
| Escrow bank | HDFC Bank Limited | |
| Other projects in this city pack | 0 |
Sources
Sources
Source URLs & documents
- https://rera.punjab.gov.in/reraindex/PublicView/GetLocations
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectPVregdprojectInfo
- https://rera.punjab.gov.in/reraindex/PublicView/ProjectViewDetails?inProject_ID=12027&inPromoter_ID=2919&inPromoterType=2
- Registration Certificate
- Approved Layout Plan
- Approved Layout Plan
- Approved Layout Plan
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Approved Project Site OR Location Map · Sign in to download
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Sanctioned Building Plan
- Authenticated Copy of Form B · Sign in to download
- CA Certificate (Form 3)
- Proforma for Undertaking- cum-Indemnity Bond · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-11-29
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-02-26
- CLU Certificate
- CLU Certificate
- Copy of Registration as Promoter · Sign in to download
- Electric Substation NOC · 2025-06-19
- Environment Clearance certificate/ NOC · 2025-02-26
- License as Promoter from competent Authority · 2023-09-22
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-12-12
- NOC from Mining Department · 2024-08-29
- NOC from NHAI/ PWD · 2024-12-17
- Occupancy Certificate from Municipal/ Competent Authority · 2024-02-06
- Other Document (Architect Experience) · 2025-02-07 · Sign in to download
- Other Document (Forest NOC) · 2025-02-10
- Other Document (Forest NOC) · 2024-11-18
- Other Document (Railway Noc) · 2024-09-02
- Other Document (RERA 70 percent designated account ) · 2024-09-25 · Sign in to download
- Other Document (Road Access NOC) · 2025-02-13
- Other Document (Road Access) · 2025-01-28 · Sign in to download
- Other Document (Solid Waste NOC) · 2024-08-08
- Pollution Clearance from Punjab Pollution Control Board · 2025-09-09
- Pollution Clearance from Punjab Pollution Control Board · 2024-09-16
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Project Land Khasra Report or Plan
- Advertisement and Brochure/ Prospectus · Sign in to download
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2024-11-29
- AAI Height NOC from Civil Aviation Department/ Airport Authority · 2025-02-26
- CLU Certificate
- CLU Certificate
- Electric Substation NOC · 2025-06-19
- Environment Clearance certificate/ NOC · 2025-02-26
- License as Promoter from competent Authority · 2023-09-22
- License to develop colony or society from Competent Authority
- License to develop colony or society from Competent Authority
- NOC from Fire Department/ Chief Fire Officer · 2024-12-12
- NOC from Mining Department · 2024-08-29
- NOC from NHAI/ PWD · 2024-12-17
- Occupancy Certificate from Municipal/ Competent Authority · 2024-02-06
- Other Document (Forest NOC) · 2025-02-10
- Other Document (Forest NOC) · 2024-11-18
- Other Document (Railway Noc) · 2024-09-02
- Other Document (Road Access NOC) · 2025-02-13
- Other Document (Solid Waste NOC) · 2024-08-08
- Pollution Clearance from Punjab Pollution Control Board · 2025-09-09
- Pollution Clearance from Punjab Pollution Control Board · 2024-09-16
- Consent details of actual owner of Land
- Consent details of actual owner of Land
- 2025-Q2 · 2025-07-15
- 2025-Q3 · 2026-01-25
- 2025-Q4 · 2026-01-25
- 2026-Q1 · 2026-04-14
- 2026-Q2 · 2026-07-12
- 2026-Q3 · 2026-10-15