SHREE RAM PARK PHASE-2

ANJANI ASSOCIATES · BILASPUR
Units178
Booked120 of 178As of 2026-06-30
Construction progress86%As of 2026-06-30
Completion2027-05-23Revised · Proposed 2027-01-23
Registered on2022-05-07

Sections

Property title & search report
Contract & costs2 cost heads · 17 quarters
Technical report
Site & area3 site details · 178 unit types
Construction & progress4 progress details · 17 quarters
Developer & finance
Developer3 developer details
The evidence
Sources96 documents · 3 source links

Registration

Registration

PromoterANJANI ASSOCIATES
DistrictBILASPUR
RegulatorCG RERA
Registration numberPCGRERA070522001413
Registered on2022-05-07
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2027-01-23
Revised completion2027-05-23