SHREE SHYAM PARK-III

SHREE SHYAM CONSTRUCTION · DURG
Units15
Booked6 of 15As of 2026-03-31
Construction progress100%As of 2026-03-31
Completion2026-10-15Proposed
Registered on2023-11-24
Approvals3

Sections

Property title & search report
Approvals3 approvals
Contract & costs2 cost heads · 10 quarters
Technical report
Site & area3 site details · 15 unit types
Construction & progress3 progress details · 10 quarters
Developer & finance
Developer3 developer details
The evidence
Sources65 documents · 6 source links

Registration

Registration

PromoterSHREE SHYAM CONSTRUCTION
DistrictDURG
RegulatorCG RERA
Registration numberPCGRERA241123001705
Registered on2023-11-24
Project typeResidential Plotted Development
Status (as filed)New
Proposed completion2026-10-15